1.2025年工程監理竣工工作總結 篇一
讓胡路區建材城(cheng)外立面改造工程(cheng)1樓、4樓、12樓經參建單位的共同努力(li),順利(li)完工。在此,我代表(biao)本(ben)工程(cheng)監理公司項目(mu)部,將本(ben)工程(cheng)監理工作情況,總結如下:
一、工程概況:
讓胡路區建(jian)材(cai)城外(wai)立面改造工(gong)(gong)(gong)(gong)(gong)程(cheng)1樓(lou)、4樓(lou)、12樓(lou),由黑(hei)龍江省廣大建(jian)筑工(gong)(gong)(gong)(gong)(gong)程(cheng)公司承包施工(gong)(gong)(gong)(gong)(gong)。該工(gong)(gong)(gong)(gong)(gong)程(cheng)主要(yao)包括土建(jian)工(gong)(gong)(gong)(gong)(gong)程(cheng)、裝飾工(gong)(gong)(gong)(gong)(gong)程(cheng)、亮(liang)化等工(gong)(gong)(gong)(gong)(gong)程(cheng)。
二、監理組(zu)織機構:
我(wo)公司根據監(jian)(jian)(jian)(jian)(jian)理合同和(he)監(jian)(jian)(jian)(jian)(jian)理大綱,結(jie)合本工(gong)程(cheng)(cheng)具體(ti)情況,組(zu)建(jian)由總監(jian)(jian)(jian)(jian)(jian)理工(gong)程(cheng)(cheng)師(shi)王立國,土(tu)建(jian)監(jian)(jian)(jian)(jian)(jian)理工(gong)程(cheng)(cheng)師(shi),電氣監(jian)(jian)(jian)(jian)(jian)理工(gong)程(cheng)(cheng)師(shi)組(zu)成(cheng)的(de)項目監(jian)(jian)(jian)(jian)(jian)理機構于20xx年6月(yue)1日進場,對本工(gong)程(cheng)(cheng)進行(xing)監(jian)(jian)(jian)(jian)(jian)理服務。項目監(jian)(jian)(jian)(jian)(jian)理組(zu)嚴格執行(xing)監(jian)(jian)(jian)(jian)(jian)理程(cheng)(cheng)序,堅持“誠信、守法(fa)、公正、科(ke)學”的(de)宗旨,以“認真、嚴謹、一絲(si)不(bu)茍”的(de)工(gong)作(zuo)(zuo)作(zuo)(zuo)風實施監(jian)(jian)(jian)(jian)(jian)理,完(wan)成(cheng)了監(jian)(jian)(jian)(jian)(jian)理任務。
三、監理(li)工作(zuo)情況:
1、抓好事(shi)前控制,嚴(yan)格開工關
在整個監理過(guo)程中,我(wo)們堅持以事(shi)前控制和主(zhu)動控制為(wei)主(zhu),依(yi)據合同和設計文(wen)件編制了監理規劃(hua),制定(ding)了具體的監理工程程序,明確了工作內容,行(xing)為(wei)主(zhu)體,驗收(shou)標準及工作要求(qiu)。
本(ben)工(gong)(gong)程開工(gong)(gong)前,依據(ju)監理規(gui)范要求(qiu),我們審查(cha)了(le)施(shi)工(gong)(gong)單位的資質(zhi),技術管(guan)理組織機構(gou)、人(ren)員、制度(du)及特殊工(gong)(gong)種操作人(ren)員的'資格、上崗證等。依據(ju)承包單位報送(song)的施(shi)工(gong)(gong)組織設計方案報審表,對施(shi)工(gong)(gong)組織設計方案進行有效審查(cha)。
2、嚴把原(yuan)材(cai)料、半成品進場(chang)關
凡是進(jin)(jin)(jin)場(chang)原(yuan)材(cai)料(liao)、半成品首先要(yao)進(jin)(jin)(jin)行(xing)書面檢(jian)(jian)(jian)查(cha)(cha),即查(cha)(cha)驗合格證、準用(yong)證、質保(bao)單等,符(fu)合要(yao)求后(hou)進(jin)(jin)(jin)行(xing)外(wai)觀檢(jian)(jian)(jian)查(cha)(cha),沒有異常(chang)情況后(hou)監理(li)見證取樣送到檢(jian)(jian)(jian)測(ce)中心復(fu)測(ce),做到材(cai)料(liao)進(jin)(jin)(jin)場(chang)先復(fu)檢(jian)(jian)(jian)后(hou)使用(yong),不合格的(de)(de)材(cai)料(liao)拒絕用(yong)于該工(gong)程相應部位。本工(gong)程建筑材(cai)料(liao)合格證、質保(bao)單齊(qi)全、對鋼材(cai)、水泥(ni)、砂、涂料(liao)等主要(yao)材(cai)料(liao)都進(jin)(jin)(jin)行(xing)了(le)進(jin)(jin)(jin)場(chang)后(hou)的(de)(de)抽檢(jian)(jian)(jian)復(fu)驗,全部達到合格要(yao)求。
3、嚴格(ge)工序檢查、強化(hua)過(guo)程控制
在施工(gong)(gong)監(jian)(jian)督過程中(zhong),強化了施工(gong)(gong)工(gong)(gong)序報(bao)驗(yan)手段,做(zuo)到(dao)先報(bao)驗(yan)后施工(gong)(gong),上道工(gong)(gong)序未(wei)經(jing)驗(yan)收不(bu)得進入下道工(gong)(gong)序的(de)(de)施工(gong)(gong),對于隱蔽(bi)工(gong)(gong)程的(de)(de)驗(yan)收我們項目監(jian)(jian)理部(bu)尤其重視,現場監(jian)(jian)理人員對重點、關鍵部(bu)位進行了旁站監(jian)(jian)督工(gong)(gong)作,如屋面(mian)防水、構建安裝等。
在監(jian)理(li)工(gong)作過(guo)程(cheng)(cheng)(cheng)中,共發出監(jian)理(li)工(gong)程(cheng)(cheng)(cheng)師通知單(dan)12份,安全隱患(huan)整(zheng)改通知單(dan)1份,在工(gong)程(cheng)(cheng)(cheng)實施過(guo)程(cheng)(cheng)(cheng)中針(zhen)對(dui)工(gong)程(cheng)(cheng)(cheng)質量(liang)、造價、進度、安全、合同管(guan)理(li)等事宜,每(mei)周召(zhao)(zhao)開工(gong)地例會,并跟(gen)進工(gong)程(cheng)(cheng)(cheng)實際情況召(zhao)(zhao)開專(zhuan)題工(gong)地例會共1次。
4、加強事(shi)后控(kong)制,確保施工質量符合合同要求
(1)、本工程在(zai)施工全(quan)過程中沒有發(fa)生質量(liang)事(shi)故,作為一步性質量(liang)問題,施工單位通(tong)(tong)過自(zi)檢、自(zi)檢后內部整(zheng)改(gai);另一方面,通(tong)(tong)過監理檢查發(fa)現后通(tong)(tong)知施工單位整(zheng)改(gai)。
(2)、及時督(du)促施工單位收集整理(li)好(hao)各種工程(cheng)資料(liao),并(bing)認真做好(hao)自己監(jian)理(li)資料(liao)。
(3)、要求施工單位做好已完工程的成品(pin)保護(hu)工作。
5、工程進度(du)控制
工(gong)(gong)程(cheng)進(jin)(jin)(jin)度的快慢直接關系(xi)到工(gong)(gong)程(cheng)建設項目能否按(an)期竣(jun)工(gong)(gong)和(he)投(tou)入(ru)使用問題。監理工(gong)(gong)程(cheng)師先(xian)審(shen)查施(shi)工(gong)(gong)單位(wei)總(zong)進(jin)(jin)(jin)度計(ji)(ji)劃(hua)(hua),并(bing)報(bao)建設單位(wei)審(shen)核同(tong)意后,督促施(shi)工(gong)(gong)單位(wei)嚴格(ge)按(an)照總(zong)進(jin)(jin)(jin)度計(ji)(ji)劃(hua)(hua)施(shi)工(gong)(gong)。并(bing)根據總(zong)進(jin)(jin)(jin)度計(ji)(ji)劃(hua)(hua)編制月進(jin)(jin)(jin)度計(ji)(ji)劃(hua)(hua),一旦發現偏差,及時要求施(shi)工(gong)(gong)單位(wei)適當調整(zheng)勞動(dong)力、材料、設備(bei)、資金,確保工(gong)(gong)程(cheng)按(an)計(ji)(ji)劃(hua)(hua)進(jin)(jin)(jin)度完成。
6、投資控制
項目監理部按照施工合同(tong)、工程施工實際進度(du)、工程質量對所監理工程進行工程款支付控制(zhi)。
7、安全生產及文明施工
“安全第一、以人為(wei)本(ben)”,在監(jian)理(li)過程(cheng)中,項目監(jian)理(li)部始終把安全監(jian)理(li)作為(wei)工(gong)(gong)作重(zhong)點,貫穿于監(jian)理(li)工(gong)(gong)作的全過程(cheng)。結合工(gong)(gong)程(cheng)實際情況,督促施工(gong)(gong)單(dan)位建(jian)立(li)安全生(sheng)產責(ze)任制,做(zuo)好安全生(sheng)產、文明施工(gong)(gong)教育(yu),定(ding)時組織(zhi)施工(gong)(gong)單(dan)位進行安全生(sheng)產檢查,對存在安全隱患(huan),及(ji)時發文要求施工(gong)(gong)單(dan)位限期整改。本(ben)工(gong)(gong)程(cheng)施工(gong)(gong)中未發生(sheng)安全事故。
通過建設(she)單位(wei)、設(she)計(ji)單位(wei)、勘察單位(wei)、承包單位(wei)、監理單位(wei)的(de)共同努(nu)力,在(zai)政(zheng)府(fu)相關部門的(de)指(zhi)導和監督下,該工(gong)程(cheng)(cheng)已按(an)照合同完成。工(gong)程(cheng)(cheng)技術資(zi)料(liao)已按(an)要(yao)求(qiu)整理,工(gong)程(cheng)(cheng)資(zi)料(liao)滿足(zu)設(she)計(ji)、規范及使用(yong)功能要(yao)求(qiu)。
在此,對參建單位對我們工作的大力(li)支持和(he)配(pei)合,表示(shi)衷心感謝!
四、工作(zuo)中(zhong)的不足:
1、施工技術力量薄(bo)弱,有(you)待加強。
2、施(shi)工(gong)單位管理人員責任心還(huan)需要加(jia)強(qiang)。
五(wu)、本工程的(de)經驗總(zong)結:
1、選擇施(shi)工隊(dui)伍必須優中選優。
2、嚴格審圖(tu),現施工(gong)隊(dui)伍技術力(li)量薄弱,不能提前(qian)發(fa)現問(wen)題,影響工(gong)程進度。
3、設計單位力量不足,尤其(qi)結(jie)構設計技術力量薄弱。
2.2025年工程監理竣工工作總結 篇二
天津市統計局機房(fang)維修改(gai)造工(gong)(gong)程(cheng)項目由中華通信(xin)系統有限責任(ren)公司中標承建,自20xx年x月(yue)開工(gong)(gong)以來(lai),在業主、監理(li)等各級領導單位和同仁們的支(zhi)持(chi)和共同幫助下,于20xx年x月(yue)底按設(she)計及規(gui)范(fan)要求完(wan)成(cheng)全部合(he)同規(gui)定及設(she)計變更(geng)的施工(gong)(gong)任(ren)務,該工(gong)(gong)程(cheng)實際共完(wan)成(cheng)投資約xx元。包括合(he)同內部及合(he)同外變更(geng)部分,該工(gong)(gong)程(cheng)從(cong)開工(gong)(gong)至完(wan)工(gong)(gong)共歷時(shi)5個月(yue)。
項目部在克(ke)服(fu)市區施(shi)工(gong)(gong)(gong)材料運輸進(jin)場困(kun)難、施(shi)工(gong)(gong)(gong)垃圾堆放場地(di)有限、之前工(gong)(gong)(gong)程(cheng)資料短缺等(deng)實際困(kun)難下,創(chuang)造性地(di)開展工(gong)(gong)(gong)作(zuo)。整個施(shi)工(gong)(gong)(gong)過程(cheng)始終圍繞了(le)開工(gong)(gong)(gong)前確定的(de)工(gong)(gong)(gong)作(zuo)思路。本著“團結、務(wu)實、優質(zhi)、高效”的(de)精神,于(yu)千頭萬緒中(zhong)努力理順(shun)工(gong)(gong)(gong)作(zuo)職(zhi)能(neng)。在任(ren)(ren)務(wu)重的(de)情況下團結奮進(jin)、扎實工(gong)(gong)(gong)作(zuo),克(ke)服(fu)了(le)種(zhong)(zhong)種(zhong)(zhong)困(kun)難,圓滿地(di)完成(cheng)了(le)天津統計(ji)局機(ji)房維修改造工(gong)(gong)(gong)程(cheng)任(ren)(ren)務(wu)。現就總(zong)體工(gong)(gong)(gong)作(zuo)情況總(zong)結如下:
一、工程概況:
天(tian)津市統計(ji)局大(da)樓座落在(zai)天(tian)津市和(he)平區(qu)南京路,天(tian)津市統計(ji)局機房維修(xiu)改(gai)造工(gong)(gong)程(cheng)項目位于大(da)樓三層(ceng),裝修(xiu)總(zong)面積約為492平方米。大(da)樓為框架結構(gou)。層(ceng)高為3.45米。此次規劃設計(ji)和(he)改(gai)造區(qu)域包括機房區(qu)域,辦(ban)公(gong)區(qu)域、過道及(ji)五層(ceng)會議室,機房區(qu)域包括中心機房及(ji)其(qi)輔助空(kong)間(jian)、監(jian)控室、鋼瓶(ping)室、配電間(jian)以及(ji)備件(jian)室,辦(ban)公(gong)區(qu)域包括辦(ban)公(gong)室、主任辦(ban)公(gong)室和(he)研(yan)討區(qu),通道包括走廊(lang)和(he)緩沖區(qu)。二層(ceng)保衛處地(di)面也在(zai)此次設計(ji)當中。本項工(gong)(gong)程(cheng)于20xx年xx月(yue)xx日正式施(shi)工(gong)(gong),20xx年xx月(yue)xx日施(shi)工(gong)(gong)結束。本項工(gong)(gong)程(cheng)質量符合(he)有關規范和(he)技術標(biao)準要求(qiu)。
二、管(guan)理方法、項目(mu)管(guan)理目(mu)標情況(kuang)
項(xiang)目部(bu)精心(xin)編制了承包實(shi)施(shi)方案,確定(ding)了三層、五層分(fen)部(bu)施(shi)工(gong)(gong)的(de)總原(yuan)則(ze),項(xiang)目管(guan)理(li)(li)中全(quan)(quan)面(mian)推行ISO9001質(zhi)量標準,確定(ding)以(yi)創建精品(pin)樣(yang)板(ban)工(gong)(gong)程(cheng)為主(zhu)線,以(yi)國家技術(shu)規范和質(zhi)量標準為依托(tuo)的(de)模式進行管(guan)理(li)(li)。在安(an)全(quan)(quan)管(guan)理(li)(li)和文明施(shi)工(gong)(gong)方面(mian)則(ze)強調大力推行標準化管(guan)理(li)(li),實(shi)行定(ding)期檢查,結(jie)合經濟(ji)獎罰制度,實(shi)現文明施(shi)工(gong)(gong)和無事故安(an)全(quan)(quan)生(sheng)產的(de)目標。
安全(quan)和文明(ming)施工管理方法:
施工(gong)(gong)(gong)期間項(xiang)目(mu)部始終把安(an)(an)(an)全(quan)(quan)(quan)(quan)、文明(ming)管理作為項(xiang)目(mu)施工(gong)(gong)(gong)重中(zhong)之重,從(cong)(cong)項(xiang)目(mu)一(yi)(yi)(yi)開工(gong)(gong)(gong),對進場每一(yi)(yi)(yi)位職(zhi)工(gong)(gong)(gong)都(dou)一(yi)(yi)(yi)一(yi)(yi)(yi)通(tong)過(guo)三(san)級安(an)(an)(an)全(quan)(quan)(quan)(quan)教(jiao)育,特殊(shu)作業工(gong)(gong)(gong)種,全(quan)(quan)(quan)(quan)部通(tong)過(guo)崗前(qian)安(an)(an)(an)全(quan)(quan)(quan)(quan)培訓,對工(gong)(gong)(gong)程中(zhong)所涉及到每個主要安(an)(an)(an)全(quan)(quan)(quan)(quan)危險(xian)源(yuan)進行列(lie)項(xiang),重點采取針對性預控措施,并對每道(dao)工(gong)(gong)(gong)序(xu)安(an)(an)(an)全(quan)(quan)(quan)(quan)施工(gong)(gong)(gong)技術(shu)進行全(quan)(quan)(quan)(quan)面(mian)交底,讓每位職(zhi)工(gong)(gong)(gong)了解工(gong)(gong)(gong)程安(an)(an)(an)全(quan)(quan)(quan)(quan)危險(xian)源(yuan)所在(zai)并能有效(xiao)預控安(an)(an)(an)全(quan)(quan)(quan)(quan)事故(gu)發(fa)生(sheng),依托獎(jiang)懲機制,加強參建民(min)工(gong)(gong)(gong)安(an)(an)(an)全(quan)(quan)(quan)(quan)教(jiao)育,從(cong)(cong)而(er)大大提高全(quan)(quan)(quan)(quan)員(yuan)安(an)(an)(an)全(quan)(quan)(quan)(quan)、文明(ming)素質,從(cong)(cong)開工(gong)(gong)(gong)至今,無一(yi)(yi)(yi)例(li)安(an)(an)(an)全(quan)(quan)(quan)(quan)、傷亡事故(gu)發(fa)生(sheng)。
三、工(gong)程質(zhi)量控制:
項目(mu)部(bu)在工程質(zhi)量(liang)(liang)控制中(zhong),堅(jian)持以公司(si)ISO9001質(zhi)量(liang)(liang)保證(zheng)體(ti)系為(wei)主線,以施工規范和國家質(zhi)量(liang)(liang)標(biao)準為(wei)準繩(sheng),遵循以下幾點(dian)原則“堅(jian)持質(zhi)量(liang)(liang)第一(yi),堅(jian)持以人為(wei)控制核心,堅(jian)持以預防為(wei)主,堅(jian)持質(zhi)量(liang)(liang)標(biao)準”貫徹科學、公正、守法的職能(neng)道德規范。
從第一道工(gong)(gong)序(xu)(xu)(xu)開(kai)始(shi)到(dao)竣工(gong)(gong)的(de)全過(guo)程,對(dui)每道工(gong)(gong)序(xu)(xu)(xu)停止檢(jian)(jian)查點提出具體的(de)技術措施(shi)、施(shi)工(gong)(gong)程序(xu)(xu)(xu)、檢(jian)(jian)驗方法(fa)和記錄(lu)要求(qiu)。對(dui)工(gong)(gong)序(xu)(xu)(xu)實行由班組“自檢(jian)(jian)”、施(shi)工(gong)(gong)員(yuan)“復(fu)檢(jian)(jian)”和質量員(yuan)“終檢(jian)(jian)”的(de)三檢(jian)(jian)制度。上道工(gong)(gong)序(xu)(xu)(xu)檢(jian)(jian)驗不合格,不準轉到(dao)下道工(gong)(gong)序(xu)(xu)(xu)。
工(gong)程出(chu)(chu)現一(yi)(yi)般(ban)不合(he)(he)格(ge)(ge),將由施(shi)(shi)工(gong)員或質(zhi)檢員監督班組(zu)進行返工(gong),直到從新檢驗合(he)(he)格(ge)(ge)為止(zhi)。還將嚴(yan)格(ge)(ge)防止(zhi)一(yi)(yi)般(ban)事(shi)故(gu)重復發生,嚴(yan)格(ge)(ge)防止(zhi)一(yi)(yi)般(ban)質(zhi)量事(shi)故(gu)通病的重復出(chu)(chu)現。重要不合(he)(he)格(ge)(ge)將由質(zhi)檢員填寫《不合(he)(he)格(ge)(ge)工(gong)序通知單(dan)》,報項目(mu)技術(shu)負責人審核、項目(mu)經理簽字,組(zu)織工(gong)程部、設計室和相關責任人員到施(shi)(shi)工(gong)現場(chang)調查分析(xi)事(shi)故(gu)發生的原(yuan)因(yin),提出(chu)(chu)糾正的措施(shi)(shi)和處理方法。
質(zhi)量活動實施(shi)和(he)控制(zhi)方(fang)法如(ru)下(xia):
圖(tu)紙交付業主(zhu)后,經業主(zhu)、監理和(he)各相關(guan)專業有關(guan)人員進行評審。
設備、材料進(jin)場時,由甲(jia)方、監理單位及(ji)本公司管理人員共同(tong)檢驗,不(bu)符合(he)合(he)同(tong)要求的產品決不(bu)能進(jin)場,以確(que)保工程(cheng)質量。
對于隱(yin)蔽(bi)工(gong)程,提(ti)前48小時通知甲方及監理單位進行(xing)(xing)中(zhong)間驗收,當隱(yin)蔽(bi)的(de)(de)工(gong)程項(xiang)目未進行(xing)(xing)隱(yin)蔽(bi)驗收時,不得(de)進行(xing)(xing)下一(yi)道工(gong)序的(de)(de)施工(gong),以確(que)保工(gong)程的(de)(de)質(zhi)量。驗收記錄存檔,竣工(gong)時作為竣工(gong)資(zi)料移交給業(ye)主。
建立質(zhi)量檢(jian)查(cha)制(zhi)度,管理人員定(ding)期進行質(zhi)量檢(jian)查(cha)并(bing)貫穿(chuan)到整個施工過(guo)程(cheng)。
各分項工程(cheng)應嚴格按操(cao)作規程(cheng)作業(ye)。
在施工過程中(zhong)由工程項目經理(li)及各子(zi)系(xi)統負責人(ren),每天不定期檢查(cha),發現質量(liang)問(wen)題當場口頭傳達解決。次日如發現問(wen)題未解決或再次發生類(lei)似的問(wen)題給(gei)予書面通知(zhi)并罰款,罰款金(jin)額(e)大小(xiao)由工程項目經理(li)酌情而(er)定。
對業主、監(jian)理(li)公(gong)司提(ti)出(chu)的(de)工程問題,核實整改后立即反饋(kui)。
質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)是企業的生(sheng)(sheng)命,項(xiang)(xiang)目(mu)(mu)部(bu)將(jiang)工(gong)(gong)(gong)程質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)定位(wei)在比較高(gao)的起點(dian),提(ti)出了項(xiang)(xiang)目(mu)(mu)質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)目(mu)(mu)標為:確保(bao)工(gong)(gong)(gong)程無質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)事故(gu)發生(sheng)(sheng),工(gong)(gong)(gong)程質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)驗收合格率100%,顧客滿(man)意度95%以上,爭創(chuang)精品樣板工(gong)(gong)(gong)程的目(mu)(mu)標。為實現(xian)這一目(mu)(mu)標,在質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)計劃中,項(xiang)(xiang)目(mu)(mu)部(bu)將(jiang)特殊過(guo)程和關鍵工(gong)(gong)(gong)序作為重點(dian)進行控(kong)制(zhi)(zhi),重點(dian)防范關鍵工(gong)(gong)(gong)序質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)問題的產(chan)生(sheng)(sheng);堅持以預防為主的原則,制(zhi)(zhi)訂消(xiao)除質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)通(tong)病計劃,將(jiang)消(xiao)除質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)通(tong)病工(gong)(gong)(gong)作放在重要的地位(wei);對各(ge)分(fen)項(xiang)(xiang)工(gong)(gong)(gong)程制(zhi)(zhi)訂出更高(gao)的質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)標準即內控(kong)標準,并經(jing)監理工(gong)(gong)(gong)程師認可后進行了實施,有(you)效的保(bao)證了各(ge)分(fen)項(xiang)(xiang)工(gong)(gong)(gong)程質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang),達到控(kong)制(zhi)(zhi)工(gong)(gong)(gong)程質(zhi)(zhi)(zhi)(zhi)量(liang)(liang)(liang)(liang)(liang)的目(mu)(mu)的。
四、組織(zhi)協調管理(li)。
本工(gong)程施(shi)工(gong)工(gong)期短、工(gong)程量(liang)大,為確保工(gong)程順(shun)利實(shi)(shi)施(shi),貫穿整個施(shi)工(gong)過(guo)程中的(de)(de)施(shi)工(gong)綜合(he)協(xie)調(diao)也是本工(gong)程的(de)(de)一大難點。在進行項(xiang)目部組織管理(li)工(gong)作(zuo)規劃(hua)時確定了如下的(de)(de)應對措(cuo)施(shi):明確分工(gong)、責(ze)任到位。項(xiang)目經理(li)負(fu)責(ze)施(shi)工(gong)全(quan)過(guo)程的(de)(de)`協(xie)調(diao)工(gong)作(zuo),檢(jian)查節點實(shi)(shi)施(shi)情況,制定、修改、調(diao)整節點計劃(hua)、協(xie)調(diao)好與業主、監理(li)、設計院的(de)(de)關系;
五、安全文明施工管理。
安(an)(an)全第一,預防為主。項目部在(zai)本工(gong)(gong)(gong)程實施過程中(zhong),將(jiang)嚴格遵(zun)照國家(jia)和(he)(he)地方的(de)有關安(an)(an)全生產法律、法規及(ji)公司的(de)相關規定,以安(an)(an)全程序為基礎直(zhi)接參(can)與活動(dong),強(qiang)化(hua)施工(gong)(gong)(gong)紀律、工(gong)(gong)(gong)藝紀律、操(cao)作紀律管理,提供(gong)必要的(de)勞動(dong)保護(hu),加強(qiang)對施工(gong)(gong)(gong)人員的(de)培(pei)訓(xun)。通過安(an)(an)全行為,促進(jin)“安(an)(an)全第一”意識提高,達(da)到“無(wu)(wu)安(an)(an)全事故”、“無(wu)(wu)人員傷(shang)亡事故”和(he)(he)“無(wu)(wu)環境污染”,實現(xian)創建施工(gong)(gong)(gong)現(xian)場安(an)(an)全質量標準化(hua)示范工(gong)(gong)(gong)程的(de)目標。
六、初驗驗收存在問(wen)題(ti)的(de)整改情(qing)況:
1、在(zai)機(ji)房區(qu)和辦公區(qu)的應急(ji)照明(ming)燈增加注釋(shi)標識。
2、機(ji)柜內部分線纜(lan)的需要重新(xin)綁扎(zha)。
3、辦公區三臺空調(diao)柜機的電源(yuan)改造。
4、五層會議(yi)室吸(xi)頂燈有兩路(lu)接觸不良。
5、五(wu)層會(hui)(hui)議(yi)室中(zhong)控系統,會(hui)(hui)議(yi)桌顯示器視頻切換的.顏色(se)失真。
七、結束語
我(wo)(wo)公司承建(jian)的(de)(de)(de)天(tian)津市(shi)統(tong)計局機房(fang)維修改造工(gong)(gong)程(cheng),經過五個月的(de)(de)(de)日夜奮戰,我(wo)(wo)們(men)(men)(men)圓(yuan)滿(man)地完成(cheng)了工(gong)(gong)程(cheng)各項(xiang)指標,工(gong)(gong)程(cheng)順利竣工(gong)(gong)。以(yi)上工(gong)(gong)作成(cheng)績沒有建(jian)設單(dan)位(wei)和(he)監理單(dan)位(wei)的(de)(de)(de)親自(zi)現(xian)場指導(dao)是達不到的(de)(de)(de),當工(gong)(gong)程(cheng)遇到困難(nan)時(shi),你們(men)(men)(men)總是幫助我(wo)(wo)們(men)(men)(men)排憂(you)解難(nan),并(bing)派遣現(xian)場代表指導(dao)工(gong)(gong)作,在(zai)此我(wo)(wo)們(men)(men)(men)真心(xin)地感(gan)謝(xie)(xie)各位(wei)領導(dao)的(de)(de)(de)支(zhi)持和(he)幫助,感(gan)謝(xie)(xie)大家這(zhe)5個月來對(dui)本工(gong)(gong)程(cheng)施(shi)(shi)工(gong)(gong)的(de)(de)(de)無(wu)(wu)私支(zhi)持。正是在(zai)各位(wei)領導(dao)的(de)(de)(de)無(wu)(wu)私關心(xin)、支(zhi)持和(he)幫助下,我(wo)(wo)們(men)(men)(men)才能夠(gou)在(zai)本項(xiang)工(gong)(gong)程(cheng)施(shi)(shi)工(gong)(gong)中取得這(zhe)么(me)好的(de)(de)(de)成(cheng)績,沒有你們(men)(men)(men)的(de)(de)(de)領導(dao)和(he)支(zhi)持就沒有今天(tian)的(de)(de)(de)輝煌(huang)成(cheng)就。后,再次向大家對(dui)我(wo)(wo)們(men)(men)(men)工(gong)(gong)作的(de)(de)(de)支(zhi)持表示(shi)由衷的(de)(de)(de)感(gan)謝(xie)(xie),謝(xie)(xie)謝(xie)(xie)!
3.2025年工程監理竣工工作總結 篇三
我于(yu)20xx年參加(jia)工(gong)(gong)作(zuo)(zuo),曾(ceng)從事表計校驗、用電檢(jian)查(cha)等(deng)工(gong)(gong)作(zuo)(zuo),現任經營部(bu)(bu)副(fu)部(bu)(bu)長,負責線損管理、計量(liang)管理、用電檢(jian)查(cha)等(deng)工(gong)(gong)作(zuo)(zuo)。在幾年的(de)實(shi)踐工(gong)(gong)作(zuo)(zuo)中,我虛心學習、刻苦鍛(duan)煉,將(jiang)書本知(zhi)識與實(shi)踐工(gong)(gong)作(zuo)(zuo)相結(jie)合,專業技術水(shui)平有了明(ming)顯提(ti)高,現將(jiang)我個人工(gong)(gong)作(zuo)(zuo)情況總結(jie)匯報如(ru)下:
一、加強標(biao)(biao)準(zhun)(zhun)設(she)備管(guan)理,確保(bao)量值(zhi)傳(chuan)遞的準(zhun)(zhun)確性。我們常說計(ji)(ji)量表計(ji)(ji)是電力(li)企業經(jing)營活動中的“秤桿子”,那末標(biao)(biao)準(zhun)(zhun)計(ji)(ji)量設(she)備則是校準(zhun)(zhun)“秤桿子”的工(gong)具,對(dui)電力(li)企業具有非(fei)同一般的重要性。我局共有標(biao)(biao)準(zhun)(zhun)設(she)備19套(tao),為保(bao)證這些設(she)備穩定(ding)健康運行,我主(zhu)持(chi)建立了標(biao)(biao)準(zhun)(zhun)計(ji)(ji)量設(she)備臺(tai)帳,明確專人(ren)管(guan)理,定(ding)期(qi)送(song)檢(jian),避免超期(qi)服役。對(dui)性能不(bu)(bu)太穩定(ding)的便(bian)攜式單相(xiang)表校驗臺(tai),我們每年由(you)(you)生產廠家維護(hu),不(bu)(bu)定(ding)期(qi)與其它標(biao)(biao)準(zhun)(zhun)做比對(dui),出現問題及時(shi)解決(jue),以免造成嚴重后果。xx年我們共送(song)檢(jian)標(biao)(biao)準(zhun)(zhun)設(she)備12套(tao),由(you)(you)于工(gong)作到位(wei)、措施(shi)得(de)力(li),送(song)檢(jian)合格率達100%,深受電研所(suo)領導的好評。
二(er)、搞(gao)好表(biao)(biao)(biao)計(ji)(ji)(ji)管(guan)理,維護供(gong)用(yong)電(dian)雙方的合法權益。通過營業性(xing)普查,我們建立(li)了(le)(le)(le)(le)表(biao)(biao)(biao)計(ji)(ji)(ji)臺帳(zhang),將計(ji)(ji)(ji)量表(biao)(biao)(biao)計(ji)(ji)(ji)納入規范化管(guan)理。我們確定了(le)(le)(le)(le)電(dian)表(biao)(biao)(biao)校(xiao)驗(yan)(yan)(yan)(yan)工作流程,由專(zhuan)人(ren)(ren)對臺帳(zhang)實(shi)(shi)(shi)(shi)行(xing)(xing)(xing)動態管(guan)理,以(yi)保證臺帳(zhang)與實(shi)(shi)(shi)(shi)際相一致。表(biao)(biao)(biao)計(ji)(ji)(ji)在校(xiao)驗(yan)(yan)(yan)(yan)前先核對臺帳(zhang),登記(ji)工作記(ji)錄,校(xiao)驗(yan)(yan)(yan)(yan)中(zhong)由微機自(zi)動記(ji)錄誤差資料,校(xiao)驗(yan)(yan)(yan)(yan)后(hou)(hou)由專(zhuan)人(ren)(ren)更改表(biao)(biao)(biao)計(ji)(ji)(ji)臺帳(zhang);若需換表(biao)(biao)(biao)則(ze)出據《計(ji)(ji)(ji)量裝置更換記(ji)錄》,并根據實(shi)(shi)(shi)(shi)際情況出據《出國留學報告(gao)書》。這(zhe)樣做的后(hou)(hou)果,有效的遏制了(le)(le)(le)(le)個(ge)別人(ren)(ren)通過電(dian)表(biao)(biao)(biao)做文(wen)章、為(wei)(wei)個(ge)人(ren)(ren)謀私利的不良(liang)行(xing)(xing)(xing)為(wei)(wei)。為(wei)(wei)保證電(dian)表(biao)(biao)(biao)校(xiao)驗(yan)(yan)(yan)(yan)質(zhi)量,我們實(shi)(shi)(shi)(shi)行(xing)(xing)(xing)電(dian)表(biao)(biao)(biao)校(xiao)驗(yan)(yan)(yan)(yan)終身負責制,電(dian)表(biao)(biao)(biao)只(zhi)要被確定為(wei)(wei)人(ren)(ren)為(wei)(wei)調整不合格誤差,不論時間多(duo)久,都(dou)要追究校(xiao)驗(yan)(yan)(yan)(yan)人(ren)(ren)的責任(ren),決不姑息(xi)。xx年,我們共校(xiao)驗(yan)(yan)(yan)(yan)電(dian)表(biao)(biao)(biao)4741塊(kuai),電(dian)流互感器(qi)4814塊(kuai),超出計(ji)(ji)(ji)劃(hua)任(ren)務56.7%,為(wei)(wei)全局(ju)降損節能提(ti)供(gong)了(le)(le)(le)(le)技術支持。
三、狠抓母(mu)線(xian)(xian)平(ping)衡(heng)管(guan)理(li),消(xiao)除(chu)線(xian)(xian)損(sun)管(guan)理(li)的(de)盲區。一般說,出國留(liu)學(xue)線(xian)(xian)損(sun)由(you)高壓(ya)線(xian)(xian)損(sun)和(he)低(di)壓(ya)線(xian)(xian)損(sun)構(gou)成(cheng),這(zhe)兩(liang)級線(xian)(xian)損(sun)均(jun)有(you)嚴格(ge)的(de)考核制度(du),受到普遍的(de)重(zhong)視;介于高低(di)壓(ya)線(xian)(xian)損(sun)之間的(de)母(mu)線(xian)(xian)平(ping)衡(heng)則很容易被忽(hu)略(lve)(lve)。而實際上,母(mu)線(xian)(xian)平(ping)衡(heng)是不允(yun)許被忽(hu)略(lve)(lve)的(de),如我(wo)局(ju)(ju)xx年(nian)全(quan)年(nian)完成(cheng)供(gong)電量(liang)(liang)(liang)(liang)(liang)2.997億(yi)kwh,若(ruo)全(quan)局(ju)(ju)母(mu)線(xian)(xian)平(ping)衡(heng)率由(you)0.5%上升到1%,全(quan)局(ju)(ju)全(quan)年(nian)擇要多損(sun)失電量(liang)(liang)(liang)(liang)(liang)149萬kwh。母(mu)線(xian)(xian)平(ping)衡(heng)率的(de)高低(di),主要取決(jue)于計(ji)量(liang)(liang)(liang)(liang)(liang)裝(zhuang)置的(de)準確(que)(que)性。為保(bao)證站(zhan)(zhan)內(nei)計(ji)量(liang)(liang)(liang)(liang)(liang)裝(zhuang)置的(de)準確(que)(que)性,xx年(nian)7月(yue)份(fen),我(wo)們將站(zhan)(zhan)內(nei)計(ji)量(liang)(liang)(liang)(liang)(liang)電表(biao)(biao)全(quan)部更(geng)換(huan)為多功能電子表(biao)(biao),并(bing)按照計(ji)量(liang)(liang)(liang)(liang)(liang)規程的(de)規定每季度(du)現(xian)場校驗(yan),確(que)(que)保(bao)表(biao)(biao)計(ji)穩(wen)定運行。通過此(ci)項工作(zuo),母(mu)線(xian)(xian)平(ping)衡(heng)率大(da)大(da)降低(di),米北、板東兩(liang)站(zhan)(zhan)平(ping)衡(heng)率由(you)原(yuan)來的(de)1.5%以上降到0.5%以內(nei),效果尤為明顯。為及時準確(que)(que)了解(jie)站(zhan)(zhan)內(nei)平(ping)衡(heng)情況,我(wo)們設專人(ren)每天都關注各站(zhan)(zhan)的(de)'平(ping)衡(heng)情況并(bing)每周核算,只要發(fa)(fa)現(xian)某個站(zhan)(zhan)連(lian)續兩(liang)天平(ping)衡(heng)率超過0.5%,便(bian)立即趕(gan)赴現(xian)場查(cha)找原(yuan)因;對各站(zhan)(zhan)上報的(de)計(ji)量(liang)(liang)(liang)(liang)(liang)故(gu)障,我(wo)們保(bao)證在12小時內(nei)人(ren)員到位,以快的(de)速(su)度(du)解(jie)決(jue)問題。xx年(nian),我(wo)們共換(huan)表(biao)(biao)46塊,現(xian)場校驗(yan)146塊次,處理(li)站(zhan)(zhan)內(nei)計(ji)量(liang)(liang)(liang)(liang)(liang)故(gu)障3起,確(que)(que)保(bao)全(quan)局(ju)(ju)全(quan)年(nian)母(mu)線(xian)(xian)平(ping)衡(heng)率在0.5%以內(nei)。為完成(cheng)供(gong)電量(liang)(liang)(liang)(liang)(liang)指(zhi)針,確(que)(que)保(bao)經濟(ji)效益,更(geng)換(huan)電子表(biao)(biao)的(de)工作(zuo)我(wo)們凌晨(chen)即出發(fa)(fa),盡量(liang)(liang)(liang)(liang)(liang)在用電低(di)谷期工作(zuo),首開我(wo)局(ju)(ju)“零點工程”先(xian)河(he)。
四、重(zhong)(zhong)視現(xian)(xian)(xian)場管理(li),全力(li)配合降損工作。現(xian)(xian)(xian)場管理(li)包括定位、驗(yan)收及多種形式(shi)的(de)(de)(de)(de)現(xian)(xian)(xian)場調(diao)(diao)查(cha)(cha)等方面的(de)(de)(de)(de)工作。每定位或驗(yan)收,我都(dou)要(yao)求(qiu)班組(zu)成員認真負責,不能局限(xian)于做記錄,而要(yao)真正(zheng)參與進(jin)去(qu),該把關的(de)(de)(de)(de)嚴格把關。xx年9月份,在(zai)對四寶革塑有限(xian)公(gong)司(si)1000kva增(zeng)容工程進(jin)行驗(yan)收時(shi),我們(men)仔細(xi)檢查(cha)(cha)接(jie)線(xian),發現(xian)(xian)(xian)了(le)廠家的(de)(de)(de)(de)計量接(jie)線(xian)錯(cuo)誤,防止了(le)一(yi)起(qi)嚴重(zhong)(zhong)計量事故的(de)(de)(de)(de)發生。對其(qi)他現(xian)(xian)(xian)場工作,無論是(shi)用電(dian)普查(cha)(cha)、還是(shi)重(zhong)(zhong)點調(diao)(diao)查(cha)(cha)某些線(xian)路、臺區(qu)(qu),還是(shi)調(diao)(diao)查(cha)(cha)公(gong)用配變的(de)(de)(de)(de)負荷情(qing)況,我都(dou)堅持實事求(qiu)是(shi)、力(li)爭將真實的(de)(de)(de)(de)第一(yi)手資料調(diao)(diao)查(cha)(cha)清楚(chu),為領導(dao)的(de)(de)(de)(de)決策提供可靠的(de)(de)(de)(de)依據(ju)。此外,我還將現(xian)(xian)(xian)場調(diao)(diao)查(cha)(cha)作為自(zi)己深入基層、接(jie)觸第一(yi)線(xian)的(de)(de)(de)(de)難得機(ji)會,通過現(xian)(xian)(xian)場調(diao)(diao)查(cha)(cha),為供電(dian)所的(de)(de)(de)(de)同志們(men)解決實際問題(ti),同時(shi)也豐富自(zi)己的(de)(de)(de)(de)閱歷,補充(chong)缺少的(de)(de)(de)(de)知識(shi)。xx年,我們(men)共調(diao)(diao)查(cha)(cha)線(xian)路30條,臺區(qu)(qu)8個(ge),糾正(zheng)錯(cuo)誤接(jie)線(xian)11處。
五、優化無(wu)功(gong)(gong)配置,為降(jiang)損工作提供(gong)(gong)(gong)技術保(bao)障。無(wu)功(gong)(gong)管(guan)理(li)是線(xian)(xian)損管(guan)理(li)中的一(yi)個重要環(huan)節,對(dui)于無(wu)功(gong)(gong)管(guan)理(li),我(wo)不滿足于供(gong)(gong)(gong)電所報幾張表、填幾個數字,而是全身心的投入到這項工作中去。我(wo)一(yi)方面(mian)深(shen)入實(shi)際、多次到北沙(sha)、東(dong)陽、大(da)步村等地,從(cong)改(gai)正無(wu)功(gong)(gong)表接線(xian)(xian)入手,幫助供(gong)(gong)(gong)電所人員(yuan)測量用(yong)戶的無(wu)功(gong)(gong)狀況、為用(yong)戶確(que)定無(wu)功(gong)(gong)補(bu)償(chang)方案、檢察無(wu)功(gong)(gong)補(bu)償(chang)效(xiao)果;另一(yi)方面(mian)查(cha)閱(yue)相關數據、了解無(wu)功(gong)(gong)補(bu)償(chang)新動態,不斷補(bu)充自己(ji)的頭腦(nao),為我(wo)局無(wu)功(gong)(gong)補(bu)償(chang)工作尋求切實(shi)可行的工作方法(fa)。通過不懈努力,供(gong)(gong)(gong)電所的同志們及不少用(yong)電戶對(dui)該項工作的認識不斷提高,去年共增無(wu)功(gong)(gong)補(bu)償(chang)量近10000kvar。
六、完成的其(qi)(qi)它(ta)工(gong)(gong)作。一年來,我除完成以上幾項(xiang)工(gong)(gong)作外,還配和其(qi)(qi)它(ta)科室完成了農電工(gong)(gong)考核、汛期揚水機(ji)站設(she)備檢查等(deng)其(qi)(qi)它(ta)工(gong)(gong)作,不(bu)再詳述。以上便是我一年來的工(gong)(gong)作情況,雖然取得了點(dian)滴(di)成績,但不(bu)足之處顯而(er)易見(jian),今后我將全力(li)改正(zheng)缺點(dian),認真學習專(zhuan)業技術知(zhi)識(shi)、提高個人素質,為圓(yuan)滿完成所(suo)承擔的各(ge)項(xiang)工(gong)(gong)作打下良好基礎(chu)。
4.2025年工程監理竣工工作總結 篇四
時(shi)光如(ru)梭,不知不覺中參加工(gong)(gong)作(zuo)(zuo)(zuo)已經一年,回首這一年的(de)(de)工(gong)(gong)作(zuo)(zuo)(zuo),遇到的(de)(de)困難和挫折不少(shao),但我必須(xu)正視,不僅要(yao)能工(gong)(gong)作(zuo)(zuo)(zuo)時(shi)埋(mai)下頭去忘我地(di)工(gong)(gong)作(zuo)(zuo)(zuo),還要(yao)能在回過頭的(de)(de)時(shi)候,對工(gong)(gong)作(zuo)(zuo)(zuo)的(de)(de)每(mei)一個細(xi)節(jie)進(jin)行檢查(cha)核(he)對,對工(gong)(gong)作(zuo)(zuo)(zuo)的(de)(de)經驗(yan)(yan)進(jin)行總結(jie)分析,從怎樣節(jie)約時(shi)間(jian),如(ru)何提高(gao)效率,盡量使工(gong)(gong)作(zuo)(zuo)(zuo)程(cheng)序化、條理化。從而在百尺(chi)桿頭,更進(jin)一步。為了更好(hao)地(di)做好(hao)今(jin)后的(de)(de)工(gong)(gong)作(zuo)(zuo)(zuo),總結(jie)經驗(yan)(yan)、吸取(qu)教訓。現將這一年的(de)(de)工(gong)(gong)作(zuo)(zuo)(zuo)心(xin)得(de)小(xiao)結(jie)如(ru)下:
一、工作方面:
1、面對眾多的變更(geng),我(wo)們駐(zhu)地監理(li)要(yao)準確了解(jie)施(shi)工(gong)情(qing)況(kuang),把握(wo)施(shi)工(gong)關鍵點(dian),在每項工(gong)程,工(gong)序開工(gong)前分(fen)(fen)析工(gong)程重點(dian),難點(dian),可(ke)能遇到(dao)的情(qing)況(kuang)和需要(yao)采取的措(cuo)施(shi),在遇到(dao)困難后和承包(bao)單位一起分(fen)(fen)析情(qing)況(kuang),研究(jiu)對策,并始終(zhong)把握(wo)“安全(quan)可(ke)靠,方便(bian)施(shi)工(gong),經濟合理(li)”的原(yuan)則(ze),嚴格審批施(shi)工(gong)單位提出(chu)的各項變更(geng),既要(yao)保(bao)證施(shi)工(gong)的順利進行,又要(yao)使費用增加額控制(zhi)在低限度。
2、圍(wei)繞促(cu)進(jin)(jin)(jin)工程(cheng)(cheng)進(jin)(jin)(jin)度這(zhe)一主(zhu)體,在(zai)不同場(chang)合,通過各種方(fang)式與承(cheng)包(bao)(bao)商(shang)共同研究、制定加快(kuai)工程(cheng)(cheng)進(jin)(jin)(jin)度的(de)措施。應從施工組(zu)織、任務承(cheng)包(bao)(bao)方(fang)式、作業面的(de)展開、工序的(de)編排等各個方(fang)面為承(cheng)包(bao)(bao)單位提出(chu)有益的(de)建議,并應及時檢查承(cheng)包(bao)(bao)商(shang)在(zai)工程(cheng)(cheng)進(jin)(jin)(jin)度方(fang)面存在(zai)的(de)不足,及時指出(chu),督促(cu)改進(jin)(jin)(jin)。
3、堅(jian)持資(zi)料真實性、及時(shi)性的同時(shi),按公司有關資(zi)料整(zheng)理(li)規定(ding),統一資(zi)料填寫的標(biao)準、方式。
4、及時監(jian)督電氣設備(bei)的(de)交接試(shi)驗(yan)工作,試(shi)驗(yan)過程(cheng)中應(ying)做好監(jian)理(li)旁站記錄,并對(dui)試(shi)驗(yan)結果的(de)各數據按照(zhao)國標及有關行(xing)業(ye)規定(ding)進行(xing)審(shen)核(he)。
5、抓工程質(zhi)量:
(1)抓(zhua)質(zhi)量意識(shi)教育,從根本上(shang)奠定高質(zhi)量的基(ji)礎。無論是工地(di)巡視,還是對(dui)工程報驗檢查,我(wo)們始(shi)終堅持對(dui)承包商說明質(zhi)量的重(zhong)要(yao)性(xing),把質(zhi)量任務落實(shi)到每(mei)個作業人員(yuan)的必要(yao)性(xing),督(du)促施工單(dan)位自覺(jue)地(di)提高工程質(zhi)量意識(shi)。
(2)嚴格(ge)堅(jian)持質量(liang)控制(zhi)的監理程序,從組織圖(tu)紙設計技術交底(di)到審(shen)批(pi)承包商的施(shi)組,承包商在具體施(shi)工中的技術指(zhi)導書和承包商對施(shi)工班組進行作業交底(di),都(dou)認真對待從不懈(xie)怠。
(3)堅持(chi)日常工(gong)程(cheng)巡查和每道工(gong)序的質(zhi)量報檢(jian)檢(jian)查,在巡查中(zhong)及時指出施(shi)工(gong)單位在材料(liao)使用,工(gong)器具(ju)準備,具(ju)體工(gong)法操作等方面的問題,令其整(zheng)改,保(bao)證了工(gong)程(cheng)質(zhi)量。
(4)對隱蔽工程、關(guan)鍵部位、關(guan)鍵工序,堅持全過程旁站與見(jian)證,做好記錄(lu)。
(5)堅持工程(cheng)例會制(zhi)度,定(ding)期召(zhao)開由監理(li)人(ren)員和承包商共(gong)同參加的工程(cheng)例會,例會上總結上周(zhou)計劃(hua)執(zhi)行情況,工程(cheng)質(zhi)量(liang)情況,找出(chu)質(zhi)量(liang)、安全文明施工中存在的問題及具體(ti)施工中遇(yu)到的困難,協調各(ge)方面(mian)努(nu)力(li)解決(jue)困難,明確下周(zhou)工程(cheng)計劃(hua),預測可能遇(yu)到的問題、困難,指出(chu)施工單(dan)位必須(xu)正(zheng)(zheng)視的問題,通過(guo)總結、預計,提高承包商在施工管理(li)、質(zhi)量(liang)控(kong)制(zhi)、安全施工等方面(mian)的水平,從而有力(li)地保證了工程(cheng)正(zheng)(zheng)常進行。
(6)堅持重(zhong)(zhong)(zhong)大(da)事情分析會制度(du),對(dui)各重(zhong)(zhong)(zhong)點工序,各重(zhong)(zhong)(zhong)大(da)事件都(dou)要召開(kai)由監(jian)理(li)人(ren)員、承包商項(xiang)目(mu)總工參加(jia)的會議,對(dui)保證工程質量解(jie)決工程難(nan)題起了重(zhong)(zhong)(zhong)大(da)作用。
(7)堅持對(dui)安(an)全(quan)(quan)(quan)(quan)生產、文明(ming)施工(gong)(gong)(gong)的(de)監督檢查工(gong)(gong)(gong)作(zuo),認真檢查承包商特(te)殊工(gong)(gong)(gong)種的(de)上(shang)崗證;基坑開挖(wa),主體結構施工(gong)(gong)(gong),強(qiang)調基坑的(de)基本(ben)安(an)全(quan)(quan)(quan)(quan)防(fang)護(hu)設施,安(an)全(quan)(quan)(quan)(quan)圍擋和過程。基坑的(de)通(tong)(tong)道、梯子要求(qiu)(qiu)施工(gong)(gong)(gong)單(dan)位(wei)不(bu)得忽視,不(bu)得圖(tu)省事過于簡陋,對(dui)施工(gong)(gong)(gong)單(dan)位(wei)不(bu)夠重視安(an)全(quan)(quan)(quan)(quan)隱患,要求(qiu)(qiu)整(zheng)改,對(dui)于電路安(an)全(quan)(quan)(quan)(quan)我們(men)亦(yi)不(bu)厭其煩(fan),老生常談,反(fan)復(fu)強(qiang)調,對(dui)各(ge)標(biao)段的(de)交(jiao)通(tong)(tong)疏解,指揮交(jiao)通(tong)(tong),安(an)全(quan)(quan)(quan)(quan)警示(shi),圍擋施工(gong)(gong)(gong)便道,材料堆放,土方運載車輛(liang)的(de)清潔沖洗(xi),我們(men)亦(yi)放在(zai)每(mei)時(shi)每(mei)刻日監理巡(xun)查日程中(zhong),發現問題及時(shi)指出,這些對(dui)施工(gong)(gong)(gong)單(dan)位(wei)的(de)安(an)全(quan)(quan)(quan)(quan)生產,文明(ming)施工(gong)(gong)(gong)都起了積極(ji)的(de)促(cu)進作(zuo)用。
二、個(ge)人學習思想方面(mian):
要學會計劃(hua)工(gong)作,學會不斷總結。必須提高自身(shen)的(de)(de)業務素質才能保質保量的(de)(de)完成工(gong)作任務。
一個沒有事(shi)業心的(de)(de)人(ren)是(shi)無法勝任(ren)監理(li)工(gong)(gong)作的(de)(de)。監理(li)人(ren)員(yuan)應把自(zi)(zi)己(ji)所服務的(de)(de)工(gong)(gong)程當作自(zi)(zi)己(ji)的(de)(de)事(shi)業來完成,工(gong)(gong)程的(de)(de)需(xu)要就是(shi)命令。勇于奉(feng)獻,服從工(gong)(gong)程整體需(xu)要,工(gong)(gong)作中切實履行合同,以對(dui)工(gong)(gong)程負責(ze)、為(wei)業主服務為(wei)宗旨。
學會吃苦耐勞、認真、負(fu)責(ze)。不(bu)(bu)(bu)管遇到什么問題(ti),不(bu)(bu)(bu)管出(chu)現(xian)(xian)了什么問題(ti),都需要(yao)(yao)(yao)(yao)虛心誠懇的(de)(de)(de)請教隨時筆(bi)記隨時總結隨時反省,絕(jue)對不(bu)(bu)(bu)允許出(chu)現(xian)(xian)自(zi)欺(qi)欺(qi)人。工作在(zai)不(bu)(bu)(bu)同(tong)的(de)(de)(de)時間段(duan)要(yao)(yao)(yao)(yao)有不(bu)(bu)(bu)同(tong)的(de)(de)(de)側重(zhong)點,這是(shi)必(bi)(bi)然的(de)(de)(de)也是(shi)必(bi)(bi)需的(de)(de)(de)。我不(bu)(bu)(bu)但(dan)要(yao)(yao)(yao)(yao)了解(jie)而且(qie)要(yao)(yao)(yao)(yao)積極的(de)(de)(de)配合。把(ba)我的(de)(de)(de)能(neng)力以團(tuan)隊的(de)(de)(de).形式發揮(hui)(hui)出(chu)來,不(bu)(bu)(bu)搞個人的(de)(de)(de)表現(xian)(xian)主義。公(gong)司(si)需要(yao)(yao)(yao)(yao)有干勁的(de)(de)(de)人,但(dan)一個人的(de)(de)(de)力量永(yong)遠是(shi)不(bu)(bu)(bu)夠的(de)(de)(de)。只要(yao)(yao)(yao)(yao)有能(neng)力,大家是(shi)有目共(gong)睹的(de)(de)(de),不(bu)(bu)(bu)但(dan)要(yao)(yao)(yao)(yao)發揮(hui)(hui)自(zi)己的(de)(de)(de)特(te)長(chang),還要(yao)(yao)(yao)(yao)會取長(chang)補(bu)短。用(yong)(yong)行(xing)動證明(ming)自(zi)己,用(yong)(yong)成(cheng)績說明(ming)自(zi)己。
在接下來的工作中準備從以下幾方面(mian)加強(qiang)。
1、要(yao)加(jia)(jia)強學習(xi),認真(zhen)提高業(ye)(ye)務、同時(shi)要(yao)拓(tuo)寬(kuan)知(zhi)(zhi)識(shi)面,在工(gong)作中(zhong)多(duo)留(liu)心相關(guan)專業(ye)(ye)知(zhi)(zhi)識(shi)的(de)汲取,使自身從土建、變電、工(gong)程(cheng)概預算等方(fang)(fang)面得到加(jia)(jia)強,滿足崗位的(de)要(yao)求。一(yi)(yi)個稱職(zhi)的(de)監(jian)理(li)人員不(bu)僅要(yao)有本(ben)專業(ye)(ye)扎(zha)實的(de)理(li)論基礎(chu)和設計(ji)(ji)、施工(gong)及管(guan)理(li)經(jing)驗,還應熟(shu)悉與(yu)本(ben)專業(ye)(ye)相關(guan)的(de)一(yi)(yi)些知(zhi)(zhi)識(shi),熟(shu)悉設計(ji)(ji)圖紙和工(gong)程(cheng)整體布置等,而且還要(yao)學習(xi)工(gong)程(cheng)管(guan)理(li)、經(jing)濟、法律法規和國家(jia)方(fang)(fang)針(zhen)政策等方(fang)(fang)面的(de)知(zhi)(zhi)識(shi)。當今(jin)世界科(ke)技高度發(fa)(fa)達(da),機(ji)電產(chan)品更新換代較(jiao)快,新技術、新工(gong)藝、新產(chan)品層出不(bu)窮,必須加(jia)(jia)強學習(xi),才(cai)能(neng)跟上時(shi)代發(fa)(fa)展的(de)需要(yao),勝任工(gong)程(cheng)監(jian)理(li)工(gong)作。
2、今后在搞好業(ye)務工(gong)作(zuo)的(de)同(tong)時,改變自身工(gong)作(zuo)作(zuo)風,不(bu)等不(bu)靠,主動出擊,積極完成各項(xiang)工(gong)作(zuo)任務,與同(tong)事(shi)間(jian)積極溝通,鼎力(li)協作(zuo),不(bu)叫苦埋怨(yuan),凡事(shi)以(yi)公司(si)利(li)益為主,積極為公司(si)創造更高價值,力(li)爭取得更大的(de)工(gong)作(zuo)成績。
3、做好外部(bu)協調工(gong)作。要(yao)主動(dong)與各方面溝通,一定要(yao)將工(gong)作做實,做細,為工(gong)程服務。
每(mei)一(yi)天(tian)都(dou)意(yi)味著新(xin)的(de)(de)(de)起(qi)點、新(xin)的(de)(de)(de)機遇(yu)、新(xin)的(de)(de)(de)挑戰(zhan),我決心在(zai)以后的(de)(de)(de)工作中揚長避(bi)短,克服不足、認真學習、勤奮工作,使自己(ji)能一(yi)直(zhi)緊跟時代發展的(de)(de)(de)步伐,為(wei)公司今后的(de)(de)(de)發展做(zuo)出(chu)應(ying)有(you)的(de)(de)(de)貢獻。
監(jian)理(li)(li)(li)工(gong)作的(de)職(zhi)責不(bu)僅(jin)賦予監(jian)理(li)(li)(li)工(gong)程師一定(ding)的(de)權利,也要求其承擔一定(ding)的(de)義(yi)務(wu)(wu)(wu)。能(neng)否(fou)處理(li)(li)(li)好(hao)二(er)者的(de)關系,對監(jian)理(li)(li)(li)工(gong)作的(de)開展很重要。只看重權利,而不(bu)履行(xing)義(yi)務(wu)(wu)(wu),甚(shen)至以權謀(mou)私,有(you)悖于(yu)監(jian)理(li)(li)(li)人員的(de)道德(de)要求,國家(jia)法(fa)(fa)律(lv)法(fa)(fa)規也不(bu)容許,無法(fa)(fa)正(zheng)常開展監(jian)理(li)(li)(li)工(gong)作。若只盡(jin)義(yi)務(wu)(wu)(wu)而放棄合(he)法(fa)(fa)權利,很多時候難(nan)以進(jin)行(xing)工(gong)程質(zhi)量、進(jin)度控(kong)制和公正(zheng)合(he)理(li)(li)(li)地處理(li)(li)(li)具(ju)體事務(wu)(wu)(wu),不(bu)僅(jin)影響自身(shen)形象,也不(bu)能(neng)切(qie)實履行(xing)監(jian)理(li)(li)(li)工(gong)程師應盡(jin)的(de)職(zhi)責。
5.2025年工程監理竣工工作總結 篇五
從本(ben)人到工(gong)地的第一天就(jiu)面對南岸(an)區安監(jian)站非常(chang)重視的邊(bian)(bian)坡治理(li)工(gong)程。此處(chu)的邊(bian)(bian)坡高度達25米,工(gong)程量大、支(zhi)護(hu)難(nan)度大、所需(xu)施工(gong)周期長,為了謀(mou)求施工(gong)進度與質量的矛盾統一,根據(ju)國家有關(guan)建(jian)設管理(li)的方針、政策(ce)、法律、法規和(he)工(gong)程建(jian)設有關(guan)的文件及監(jian)理(li)細則。
我(wo)監理部對施(shi)工(gong)進(jin)行了(le)“事(shi)前預控(kong)”、“事(shi)中控(kong)制”以(yi)及(ji)“事(shi)后控(kong)制”。高邊(bian)坡(po)支護受雨季、惡(e)劣天氣影響較大,除加強(qiang)量測(ce)監控(kong)外,還必須結合開挖(wa)工(gong)藝做(zuo)(zuo)好(hao)排水措(cuo)施(shi),以(yi)及(ji)坡(po)面、坡(po)頂防雨水沖刷措(cuo)施(shi)和(he)坡(po)腳加固措(cuo)施(shi)。特(te)別(bie)是(shi)p1—s1段(duan)邊(bian)坡(po)鄰(lin)近(jin)110KV的(de)(de)高壓(ya)鐵(tie)塔,本人以(yi)及(ji)我(wo)監理部人員對該段(duan)邊(bian)坡(po)進(jin)行特(te)別(bie)的(de)(de)時時監控(kong),做(zuo)(zuo)好(hao)每天的(de)(de)監控(kong)日志(zhi),且督促施(shi)工(gong)單位對該段(duan)坡(po)面鄰(lin)近(jin)的(de)(de)高壓(ya)鐵(tie)塔進(jin)行必要的(de)(de)防護,做(zuo)(zuo)好(hao)坡(po)面防雨措(cuo)施(shi)。
20xx年x月xx日至(zhi)今,本人從進公司以(yi)來一直在(zai)盤龍花園二期農轉(zhuan)非安置住宅工(gong)(gong)(gong)程(cheng)擔任監理(li)員工(gong)(gong)(gong)作(zuo)。我(wo)始終堅持以(yi)一個合格(ge)的(de)(de)監理(li)員的(de)(de)標準(zhun)要求自己(ji),熱愛自己(ji)的(de)(de)本職工(gong)(gong)(gong)作(zuo);有良(liang)好(hao)的(de)(de)工(gong)(gong)(gong)作(zuo)作(zuo)風和吃苦耐勞精神(shen);工(gong)(gong)(gong)作(zuo)態度(du)嚴謹,思想品(pin)德端(duan)正(zheng);遵守國(guo)家(jia)的(de)(de)法(fa)律、法(fa)規(gui)以(yi)及(ji)企業(ye)的(de)(de)規(gui)章制度(du);服(fu)從組(zu)織的(de)(de)分配,吃苦在(zai)前(qian),享(xiang)受在(zai)后(hou),盡(jin)職盡(jin)責。認真(zhen)完成監理(li)部交給我(wo)的(de)(de)各(ge)項(xiang)工(gong)(gong)(gong)作(zuo)。日常工(gong)(gong)(gong)作(zuo)中能(neng)高標準(zhun)嚴要求自己(ji),嚴格(ge)履行自己(ji)的(de)(de)崗(gang)位職責,站在(zai)公正(zheng)的(de)(de)立(li)(li)場上,獨立(li)(li)地解決(jue)實際問題。生活中,能(neng)夠尊重領導,團結同事。
本人堅(jian)持對原材(cai)料、機械(xie)設備的(de)(de)進(jin)場(chang)進(jin)行(xing)進(jin)行(xing)審查是否與(yu)施(shi)工方案、工藝要求相配套;檢查鋼筋等原材(cai)料的(de)(de)加工質量(liang)及存放條件,并現場(chang)檢測基使用性(xing)能(neng);施(shi)工設備應(ying)充(chong)分(fen)發揮作(zuo)業效率,保證施(shi)工的(de)(de)質量(liang)及進(jin)度。堅(jian)持做好原材(cai)料見證取樣,以及重要工序、重要部位的(de)(de)旁(pang)站工作(zuo),且做好旁(pang)站日記。
工(gong)(gong)(gong)(gong)程(cheng)(cheng)質量(liang)(liang)方(fang)面(mian),根據(ju)監(jian)理規范(fan)、工(gong)(gong)(gong)(gong)程(cheng)(cheng)圖紙和《監(jian)理細則(ze)》嚴格(ge)監(jian)督。我大(da)部分時(shi)(shi)間(jian)都在工(gong)(gong)(gong)(gong)地(di)現(xian)場(chang),工(gong)(gong)(gong)(gong)地(di)范(fan)圍(wei)大(da),多點(dian)同時(shi)(shi)施(shi)(shi)工(gong)(gong)(gong)(gong),必須抓住監(jian)理重點(dian)才能減少工(gong)(gong)(gong)(gong)作量(liang)(liang)的(de)同時(shi)(shi)又能提(ti)高工(gong)(gong)(gong)(gong)作效率和效果。如(ru)果發現(xian)自己解(jie)決不了(le)的(de)問題(ti)及(ji)(ji)時(shi)(shi)的(de)向專業監(jian)理工(gong)(gong)(gong)(gong)程(cheng)(cheng)師及(ji)(ji)總監(jian)理工(gong)(gong)(gong)(gong)程(cheng)(cheng)師匯報并查閱相關規范(fan)。對(dui)于有交叉作業的(de)的(de)工(gong)(gong)(gong)(gong)程(cheng)(cheng),現(xian)場(chang)協調各施(shi)(shi)工(gong)(gong)(gong)(gong)單位的(de)施(shi)(shi)工(gong)(gong)(gong)(gong)順序,力求達到。每個月末將現(xian)場(chang)情況與施(shi)(shi)工(gong)(gong)(gong)(gong)計劃進行核對(dui),如(ru)果進度落(luo)后及(ji)(ji)時(shi)(shi)要求施(shi)(shi)工(gong)(gong)(gong)(gong)單位在保(bao)證(zheng)工(gong)(gong)(gong)(gong)程(cheng)(cheng)質量(liang)(liang)及(ji)(ji)施(shi)(shi)工(gong)(gong)(gong)(gong)安全的(de)前提(ti)下采取措(cuo)施(shi)(shi)加快施(shi)(shi)工(gong)(gong)(gong)(gong)。
工程(cheng)資(zi)料(liao)(liao)方(fang)面,每天根據工地現場(chang)情況寫好(hao)監(jian)理日記(ji)(ji),并將當(dang)天的旁站記(ji)(ji)錄等(deng)資(zi)料(liao)(liao)整理歸檔,督促(cu)施(shi)工單(dan)位上報相應(ying)的工程(cheng)資(zi)料(liao)(liao)。定期將見(jian)證(zheng)取樣、平(ping)等(deng)檢測等(deng)資(zi)料(liao)(liao)整改歸檔,并且(qie)將各項(xiang)的臺賬做好(hao),力求(qiu)在工程(cheng)結束時資(zi)料(liao)(liao)也備齊歸檔。
一、工作中體會感(gan)受(shou)
通過(guo)半年(nian)(nian)的(de)監(jian)理工(gong)(gong)(gong)(gong)作(zuo),我(wo)覺(jue)得我(wo)作(zuo)為一(yi)名監(jian)理人(ren)員(yuan)只有做到品行(xing)端(duan)正、嚴于(yu)律已、融入團隊(dui)、尊(zun)重他人(ren)、工(gong)(gong)(gong)(gong)作(zuo)認真負責才會(hui)贏得別(bie)人(ren)的(de)尊(zun)重。在(zai)工(gong)(gong)(gong)(gong)地上我(wo)學(xue)習(xi)到了很多東西,在(zai)同事的(de)細(xi)心(xin)指(zhi)導、幫助下我(wo)學(xue)到了很多新(xin)的(de)理論知識(shi)和實踐經驗(yan),拓寬了我(wo)的(de)知識(shi)面。這半年(nian)(nian)的(de)工(gong)(gong)(gong)(gong)作(zuo)我(wo)收獲很大(da),但也存(cun)在(zai)很多的(de)不足,工(gong)(gong)(gong)(gong)作(zuo)經驗(yan)不足,面對強度較大(da)的(de)工(gong)(gong)(gong)(gong)作(zuo)的(de)時候不夠(gou)細(xi)致(zhi),不夠(gou)耐心(xin),這些不足也導致(zhi)自己的(de)`工(gong)(gong)(gong)(gong)作(zuo)存(cun)在(zai)很多的(de)瑕疵。在(zai)以(yi)后的(de)工(gong)(gong)(gong)(gong)作(zuo)中我(wo)會(hui)勤(qin)學(xue)習(xi),不斷(duan)總結(jie)經驗(yan),吸取教訓,改正自己的(de)不足爭取做到揚(yang)長避(bi)短。
二、明年個人職(zhi)業(ye)發展方(fang)向
從事(shi)監(jian)理工(gong)(gong)作,懂得再多(duo)也嫌少(shao),絕不對滿足于現在,因此我(wo)明年依然要(yao)多(duo)問(wen)、多(duo)學(xue)、多(duo)做,按照工(gong)(gong)作需要(yao)逐(zhu)步深入(ru)的(de)學(xue)習好各項(xiang)專(zhuan)業知識。工(gong)(gong)作生活上遵(zun)守公(gong)司的(de)各項(xiang)管理制度(du),加強團隊意識培養,進一(yi)步融入(ru)我(wo)們這個集(ji)體,并且利用業余的(de)時間多(duo)學(xue)習一(yi)些(xie)規范多(duo)看一(yi)些(xie)相關的(de)論文,提(ti)高自己(ji)(ji)的(de)業務水(shui)平(ping)。使自己(ji)(ji)能更好的(de)適應這份工(gong)(gong)作,發(fa)揮(hui)自己(ji)(ji)的(de)力量為公(gong)司做應有(you)的(de)貢獻。
6.2025年工程監理竣工工作總結 篇六
一、本(ben)工程主要參(can)建(jian)單位(wei):
略。
二、工程概況:
本(ben)工(gong)程為(wei)(wei)(wei)麗(li)水市市區(qu)(qu)(qu)老(lao)小(xiao)(xiao)區(qu)(qu)(qu)改造(zao)(zao)工(gong)程(緊電小(xiao)(xiao)區(qu)(qu)(qu))位于麗(li)水市市區(qu)(qu)(qu)白(bai)(bai)云小(xiao)(xiao)區(qu)(qu)(qu)白(bai)(bai)云路(lu)(lu)的(de)西側,四面有(you)圍(wei)墻,在白(bai)(bai)云路(lu)(lu)側有(you)一主(zhu)兩次三個開(kai)口(kou)。該小(xiao)(xiao)區(qu)(qu)(qu)是上世紀(ji)八、九(jiu)十年(nian)代建造(zao)(zao),小(xiao)(xiao)區(qu)(qu)(qu)內共8幢房(fang)子,161戶住戶。本(ben)次改造(zao)(zao)工(gong)程總用地(di)面積(ji)為(wei)(wei)(wei)8055.6平(ping)方米(mi),室外道(dao)路(lu)(lu)面積(ji)為(wei)(wei)(wei)1990.1平(ping)方米(mi)(包括小(xiao)(xiao)區(qu)(qu)(qu)主(zhu)道(dao)路(lu)(lu)與宅旁(pang)道(dao)路(lu)(lu)),建筑占地(di)面積(ji)為(wei)(wei)(wei)2654.4平(ping)方米(mi)。設計綠(lv)化面積(ji)為(wei)(wei)(wei)2654.4平(ping)方米(mi)、綠(lv)化綠(lv)化覆(fu)蓋率為(wei)(wei)(wei)33%、綠(lv)地(di)面積(ji)為(wei)(wei)(wei)2353平(ping)方米(mi)、綠(lv)化率為(wei)(wei)(wei)29.2%,施工(gong)范圍(wei)為(wei)(wei)(wei)小(xiao)(xiao)區(qu)(qu)(qu)綠(lv)化。該工(gong)程于20xx年(nian)7月(yue)26日(ri)開(kai)工(gong),20xx月(yue)12月(yue)完成了(le)合(he)同約定的(de)全部施工(gong)內容(rong),并經業(ye)主(zhu)單位組織(zhi)了(le)預(yu)驗(yan)(yan),具備了(le)竣工(gong)驗(yan)(yan)收(shou)條(tiao)件,現將有(you)關情況予以(yi)報(bao)告,請(qing)核驗(yan)(yan)。
麗水市(shi)市(shi)區(qu)老小(xiao)(xiao)區(qu)改造(zao)工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)(緊電(dian)小(xiao)(xiao)區(qu))受麗水市(shi)蓮(lian)都區(qu)建(jian)設(she)發展有(you)限公司所(suo)委托由本公司進(jin)(jin)行(xing)工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)監(jian)(jian)(jian)理(li)(li)(li),工(gong)(gong)(gong)(gong)(gong)規(gui)范(fan)、質量檢驗評(ping)定標(biao)準、相關的標(biao)準圖(tu)集(ji)和(he)施(shi)工(gong)(gong)(gong)(gong)(gong)單位(wei)(wei)的施(shi)工(gong)(gong)(gong)(gong)(gong)組織設(she)計(施(shi)工(gong)(gong)(gong)(gong)(gong)方案),結合項(xiang)目監(jian)(jian)(jian)理(li)(li)(li)規(gui)劃和(he)監(jian)(jian)(jian)理(li)(li)(li)細則的要求,在建(jian)設(she)單位(wei)(wei)、設(she)計單位(wei)(wei)的協助下,在質監(jian)(jian)(jian)站的指導下,進(jin)(jin)行(xing)施(shi)工(gong)(gong)(gong)(gong)(gong)監(jian)(jian)(jian)理(li)(li)(li)。根(gen)據工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)情(qing)況及監(jian)(jian)(jian)理(li)(li)(li)范(fan)圍,公司組建(jian)了項(xiang)目監(jian)(jian)(jian)理(li)(li)(li)班(ban)子(zi),安排專業監(jian)(jian)(jian)理(li)(li)(li)工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)師對(dui)市(shi)政道路、給排水、綠化等工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)進(jin)(jin)行(xing)全過程(cheng)(cheng)監(jian)(jian)(jian)理(li)(li)(li)工(gong)(gong)(gong)(gong)(gong)作(zuo)。在監(jian)(jian)(jian)理(li)(li)(li)工(gong)(gong)(gong)(gong)(gong)作(zuo)實施(shi)中執行(xing)了主要材(cai)料(liao)、購配件的進(jin)(jin)場(chang)報驗、分項(xiang)工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)的施(shi)工(gong)(gong)(gong)(gong)(gong)質量檢查(cha)、工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)技術資(zi)料(liao)的審核(he)等一系列制度,為使本工(gong)(gong)(gong)(gong)(gong)程(cheng)(cheng)在施(shi)工(gong)(gong)(gong)(gong)(gong)中能符合設(she)計和(he)質量標(biao)準的要求,監(jian)(jian)(jian)理(li)(li)(li)人員對(dui)施(shi)工(gong)(gong)(gong)(gong)(gong)過程(cheng)(cheng)進(jin)(jin)行(xing)了認真負責的監(jian)(jian)(jian)理(li)(li)(li)。
三(san)、監理主要包括以下工作內容(rong):
1、管溝土石方開(kai)(kai)挖:采用挖機(ji)(ji)開(kai)(kai)挖與人工相結合,遇巖層(ceng)時采用液(ye)壓式破(po)碎機(ji)(ji)破(po)除。
2、路基填(tian)筑(zhu):清除表土、淤泥質土換填(tian),路基整平、分層填(tian)筑(zhu)碾壓,不宜(yi)壓路機碾壓時采(cai)用打夯(hang)機夯(hang)實,保證壓實度(du)。
3、基(ji)層及(ji)路面澆(jiao)注(zhu):基(ji)層采用25cm(人(ren)行道15cm)厚5%水泥穩定碎石(shi),在(zai)初凝前(qian)完成壓實,基(ji)層彎沉要(yao)求(qiu)大于95Mpa。混(hun)凝土所用粗細集(ji),填料(liao)以及(ji)瀝(li)青均應(ying)符合(he)合(he)同技術規范要(yao)求(qiu),并至少(shao)在(zai)工程(cheng)開(kai)始前(qian)一個月將(jiang)推薦混(hun)合(he)料(liao)配合(he)比包括(kuo):礦(kuang)料(liao)級配、瀝(li)青含量(liang)、穩定度包括(kuo)隙(xi)率等的詳(xiang)細說明。
4、管道工程:
塑料成品檢(jian)查井:
雨(yu)污水(shui)(shui)檢查(cha)(cha)井(jing)(jing)均采(cai)(cai)用塑(su)(su)料成(cheng)品檢查(cha)(cha)井(jing)(jing),宅(zhai)間道路上的(de)井(jing)(jing)筒(tong)采(cai)(cai)用(upvc)平壁中(zhong)空(kong)管井(jing)(jing)筒(tong),小區主道路上的(de)井(jing)(jing)筒(tong)采(cai)(cai)用(HDPE)中(zhong)空(kong)纏(chan)繞管井(jing)(jing)筒(tong),環剛度不小于(yu)8KN/M2,井(jing)(jing)筒(tong)高度根據埋深現場(chang)下料;檢查(cha)(cha)井(jing)(jing)基(ji)礎一般(ban)土(tu)質(zhi)采(cai)(cai)用10cm中(zhong)粗(cu)砂基(ji)礎,較(jiao)差土(tu)質(zhi)時(shi),先(xian)鋪設10cm的(de)碎石墊(dian)層,夯實后再敷(fu)設10cm中(zhong)粗(cu)砂基(ji)礎。所用塑(su)(su)料成(cheng)品檢查(cha)(cha)井(jing)(jing)和雨(yu)水(shui)(shui)口及相(xiang)關(guan)配件均應符(fu)合國家相(xiang)關(guan)技術指(zhi)標。
井蓋
雨、污(wu)水檢查井(jing)均(jun)設置防(fang)護井(jing)蓋(gai)【由(you)廠家根據井(jing)筒(tong)尺寸配套提供】雨水、污(wu)水井(jing)蓋(gai)均(jun)采用(yong)重(zhong)型(xing)復合(he)(he)(he)材料的(de)井(jing)蓋(gai)【宅間為重(zhong)型(xing),主道路為加重(zhong)型(xing)】,防(fang)護井(jing)蓋(gai)基座法詳見相(xiang)關圖紙。復合(he)(he)(he)井(jing)蓋(gai)的(de)承載(zai)力要(yao)(yao)求必須符合(he)(he)(he)cj/t211-20xx【聚(ju)合(he)(he)(he)物(wu)基復合(he)(he)(he)材料檢查井(jing)蓋(gai)】的(de)'要(yao)(yao)求。
塑料成品雨水口
底(di)座采(cai)用注(zhu)塑成型工(gong)藝,井筒采(cai)用平壁中(zhong)空管,環剛度不小(xiao)于8K/M2,井簡高渡(du)根據埋深現(xian)場下料(liao);基(ji)礎與塑料(liao)成品(pin)檢查井相同。雨水口(kou)井蓋底(di)座法(fa)詳見相關圖紙(zhi),其(qi)他工(gong)藝安裝(zhuang)及做法(fa)參(can)考國(guo)際08SS523/27,雨水口(kou)箅子采(cai)用400x500復合雨水箅子。
5、綠化:
1)、做(zuo)好施(shi)工(gong)之前的(de)組織設計(方(fang)案)審(shen)(shen)查監(jian)理人員(yuan)對施(shi)工(gong)單位的(de)施(shi)工(gong)方(fang)案進行(xing)詳(xiang)細的(de)審(shen)(shen)查做(zuo)到施(shi)工(gong)方(fang)法先進,技術合(he)理,安全(quan)文(wen)明施(shi)工(gong),有利于(yu)提高工(gong)程質量(liang)。
2)、嚴(yan)格(ge)(ge)控(kong)制(zhi)園林綠化(hua)材料的(de)質(zhi)量(liang)嚴(yan)格(ge)(ge)控(kong)制(zhi)投入材料的(de)質(zhi)量(liang)是確保(bao)工程(cheng)質(zhi)量(liang)的(de)前提。本工程(cheng)苗(miao)(miao)木(mu)進場共3批(pi)次,進場的(de)闊葉麥冬、石蒜等監(jian)理(li)工程(cheng)師按照設(she)計要求逐(zhu)株進行(xing)了測量(liang),灌木(mu)及草(cao)本植物采取抽(chou)測的(de)方法(fa),對(dui)不符要求的(de)苗(miao)(miao)木(mu)一律(lv)清退(tui),且不得用于工程(cheng)。對(dui)于苗(miao)(miao)木(mu)的(de)材料報驗要求施工單位做到(dao)及時有序(xu)。從(cong)貨源到(dao)使用認證,嚴(yan)格(ge)(ge)做到(dao)層(ceng)層(ceng)把關。
3)、種(zhong)植(zhi)(zhi)前(qian)的(de)施工(gong)質量(liang)監控監理工(gong)程師(shi)要求施工(gong)單(dan)位栽植(zhi)(zhi)前(qian)的(de)場地整理、種(zhong)植(zhi)(zhi)穴的(de)大小(xiao)、深度、種(zhong)植(zhi)(zhi)的(de)苗(miao)木以(yi)及栽植(zhi)(zhi)過程均嚴格按照綠化工(gong)程相關技術規范執行。同時要求施工(gong)單(dan)位選擇肥沃(wo)、疏(shu)松、排水良好的(de)種(zhong)植(zhi)(zhi)土(tu)壤,栽植(zhi)(zhi)土(tu)的(de)PH值(zhi)(zhi)應控制(zhi)在6.5—7.5,對喜酸性(xing)的(de)樹(shu)木PH值(zhi)(zhi)控制(zhi)在5—6.5,對于不(bu)適合(he)樹(shu)木生長(chang)的(de)栽植(zhi)(zhi)土(tu)進行換土(tu)處(chu)理。每道工(gong)序驗收合(he)格后,才可以(yi)進入下一道工(gong)序。
4)、種植過程中(zhong)施工(gong)質量監(jian)控剪,保留骨架(jia)摘去大(da)部分樹葉,以減少(shao)植株的水(shui)分蒸發(fa)。種植時(shi)土球(qiu)經初步覆土塞實(shi)后可將土球(qiu)包扎物(wu)自上(shang)而下小心解除,隨后填(tian)土,分層搗實(shi),待填(tian)土達土球(qiu)深(shen)度的1∕3時(shi),邊填(tian)土邊灌水(shui),澆足第(di)水(shui)。
5)、督(du)促施(shi)工(gong)單位(wei)加(jia)(jia)強園(yuan)(yuan)(yuan)林(lin)綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)工(gong)程(cheng)后(hou)(hou)期養護(hu)(hu)(hu)(hu)管(guan)(guan)理(li)加(jia)(jia)強園(yuan)(yuan)(yuan)林(lin)綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)工(gong)程(cheng)后(hou)(hou)期養護(hu)(hu)(hu)(hu)管(guan)(guan)理(li)是(shi)(shi)園(yuan)(yuan)(yuan)林(lin)綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)工(gong)程(cheng)質量(liang)監理(li)與控(kong)制的(de)(de)重要(yao)環(huan)節。本(ben)工(gong)程(cheng)合同要(yao)求的(de)(de)養護(hu)(hu)(hu)(hu)期,目(mu)的(de)(de)就是(shi)(shi)確(que)保綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)苗(miao)木(mu)成活(huo),生長良(liang)好。園(yuan)(yuan)(yuan)林(lin)綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)工(gong)程(cheng)后(hou)(hou)期養護(hu)(hu)(hu)(hu)管(guan)(guan)理(li)是(shi)(shi)苗(miao)木(mu)成活(huo)的(de)(de)關鍵,如果園(yuan)(yuan)(yuan)林(lin)綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)工(gong)程(cheng)施(shi)工(gong)優(you)良(liang),但綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)養護(hu)(hu)(hu)(hu)管(guan)(guan)理(li)不(bu)到(dao)(dao)位(wei),將嚴重影響園(yuan)(yuan)(yuan)林(lin)綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)工(gong)程(cheng)景觀效(xiao)果,影響工(gong)程(cheng)質量(liang)。俗話說:“三(san)分栽(zai),七分管(guan)(guan)”,如果后(hou)(hou)期養護(hu)(hu)(hu)(hu)管(guan)(guan)理(li)不(bu)到(dao)(dao)位(wei),如澆水(shui)不(bu)及時,導致(zhi)樹木(mu)成活(huo)率低;樹木(mu)支(zhi)架不(bu)牢,導致(zhi)栽(zai)植樹木(mu)歪斜;除草不(bu)及時,導致(zhi)綠(lv)(lv)(lv)地雜草叢(cong)生;打藥治蟲不(bu)及時,導致(zhi)病蟲害嚴重等質量(liang)問題。因此,必須加(jia)(jia)強園(yuan)(yuan)(yuan)林(lin)綠(lv)(lv)(lv)化(hua)(hua)(hua)(hua)工(gong)程(cheng)后(hou)(hou)期養護(hu)(hu)(hu)(hu)管(guan)(guan)理(li)工(gong)作(zuo),確(que)保工(gong)程(cheng)質量(liang)。在(zai)這點(dian)上(shang)我們督(du)促施(shi)工(gong)單位(wei)針(zhen)對(dui)每個季節的(de)(de)特(te)點(dian)制定(ding)了(le)詳細的(de)(de)養護(hu)(hu)(hu)(hu)計劃并形(xing)成一套完整(zheng)的(de)(de)養護(hu)(hu)(hu)(hu)臺賬,預驗(yan)收會議監理(li)工(gong)程(cheng)師(shi)重點(dian)要(yao)求施(shi)工(gong)單位(wei)加(jia)(jia)強對(dui)香樟的(de)(de)冬季管(guan)(guan)養工(gong)作(zuo)。
四、監理情況:
一)、審核(he)施工(gong)組織設計(施工(gong)方案)。
二)、對進(jin)(jin)入施工(gong)現場的主要(yao)材料(如鋼筋、水(shui)泥、標準磚(zhuan)等),檢查(cha)其(qi)數量(liang)、規格(ge)(ge),核(he)查(cha)出(chu)廠合(he)格(ge)(ge)證,在(zai)符合(he)要(yao)求(qiu)的基礎上按規定進(jin)(jin)行見(jian)證取樣、送樣檢測復試,經試驗合(he)格(ge)(ge)后才允許(xu)該批材料在(zai)工(gong)程(cheng)中使(shi)用,凡不(bu)合(he)格(ge)(ge)的材料不(bu)得使(shi)用。
見證(zheng)取樣(yang)材(cai)料(liao)(liao)及構配(pei)件為:鋼材(cai)(HRB400ф12、HRB400ф10、HPB300ф8)、水(shui)泥(復合(he)(he)32.5)、瀝青混合(he)(he)料(liao)(liao)配(pei)合(he)(he)比、塘渣(zha)、無極結合(he)(he)料(liao)(liao)穩定材(cai)料(liao)(liao)配(pei)合(he)(he)比、混凝土路面磚(Cc30)、管(guan)材(cai)(110x3.2)、井蓋(gai)(ф600)、瀝青混合(he)(he)料(liao)(liao)等經質監站(zhan)抽檢合(he)(he)格。
1)道路(lu)工程:無側限抗壓試(shi)塊(kuai)2組,合格。
2)排水(shui)工程C30試(shi)塊共1組,合(he)格。
三)、道路測量(liang)放線、高程(cheng)測量(liang):
根據業主(zhu)提供的坐標基準點和原(yuan)始高程點引(yin)測(ce)(ce),測(ce)(ce)量(liang)復核(he)滿足閉合(he)差要(yao)求(qiu),經測(ce)(ce)繪大隊竣工檢測(ce)(ce)符合(he)要(yao)求(qiu)。管(guan)線、路(lu)基、路(lu)面(mian)高程偏差在(zai)誤差允許范(fan)圍內,路(lu)寬、坡度、線直(zhi)等偏差符合(he)規范(fan)規定(ding)。
四)、雨、污(wu)管(guan)線(xian)工程:
管(guan)線溝槽槽底土質情況較(jiao)好;管(guan)線鋪設符合設計(ji)及規范(fan)要求,閉水(shui)試(shi)驗(yan)合格;管(guan)道回填壓實(shi)度按標準取樣檢(jian)測,壓實(shi)度試(shi)驗(yan)合格;成品檢(jian)查(cha)井質量合格,符合設計(ji)要求。各項(xiang)工(gong)序基本按規定進行隱蔽驗(yan)收,各項(xiang)工(gong)序評定達到合格標準。
五)、電力、電信、供(gong)水管線:
依(yi)據設(she)計(ji)圖(tu)紙及現場情況(kuang),按照規(gui)(gui)范規(gui)(gui)定鋪設(she),檢查(cha)井設(she)置符合設(she)計(ji)要求(qiu),各工序質量(liang)評定、分項工程均達(da)到合格標(biao)準(zhun)。
六)、路基工(gong)程(cheng):
多(duo)為(wei)石(shi)方填筑,局部道(dao)路段(duan)淤泥土(tu)、根植土(tu)換填,路基機(ji)械整平,人工修整,12t壓路機(ji)壓實。土(tu)基壓實度根據規(gui)范規(gui)定頻率取樣(yang),經檢壓實度試驗合格。
七(qi))、綠化工程(cheng):
面積(ji)2654.4平(ping)方米(mi),苗(miao)木品種有闊葉麥(mai)冬(dong)、石蒜、花卉、馬(ma)尼拉等品種,綠(lv)化工(gong)(gong)(gong)程采(cai)用先土(tu)(tu)方后(hou)(hou)(hou)種植,先大塊(kuai)(kuai)后(hou)(hou)(hou)小塊(kuai)(kuai)的(de)原則安排施工(gong)(gong)(gong)順序。進場后(hou)(hou)(hou)___,清(qing)除(chu)綠(lv)地(di)范圍內的(de)建筑垃圾(ji),對(dui)綠(lv)地(di)范圍建筑垃圾(ji)采(cai)用機械清(qing)理外(wai)運(yun),按(an)設計(ji)圖紙進行土(tu)(tu)方初步(bu)(bu)造(zao)型后(hou)(hou)(hou),采(cai)用人工(gong)(gong)(gong)人工(gong)(gong)(gong)調整進一步(bu)(bu)造(zao)型,使坡面曲(qu)線自然(ran)和順,形態柔(rou)和,無明(ming)顯的(de)起伏,標高符(fu)合設計(ji)要(yao)求(qiu)(qiu);在清(qing)理的(de)同時(shi),土(tu)(tu)壤(rang)顆粒給予切細,不允許出(chu)現(xian)高低懸殊,坑洼(wa)現(xian)象。綠(lv)化做到苗(miao)木品種正確無誤,生長旺盛(sheng),姿態豐滿,品種優良,規(gui)格符(fu)合設計(ji)要(yao)求(qiu)(qiu)。
麗水市(shi)市(shi)區老(lao)小(xiao)區改造工(gong)程(緊(jin)電小(xiao)區)工(gong)程共分為路基、基層(ceng)(ceng)、面層(ceng)(ceng)、人(ren)行道(dao)、附屬構筑物、排(pai)水、綠(lv)化7個(ge)分部工(gong)程,經查,均合格。
項(xiang)目監理(li)部在(zai)各部門的大力關心、指導下,在(zai)設(she)計單位(wei)、建設(she)單位(wei)的緊密配合支持(chi)下,經過施工單位(wei)組織施工,按計劃、保(bao)質量、保(bao)安全地完(wan)成了任務(wu)。我公司為(wei)能夠在(zai)麗水市(shi)蓮(lian)都區建設(she)發展(zhan)有限公司的開(kai)發建設(she)中盡一份心、出一份力而感到榮(rong)幸。
7.2025年工程監理竣工工作總結 篇七
xx擴建(jian)工(gong)程自xx年(nian)(nian)xx月開(kai)工(gong),歷經(jing)近1年(nian)(nian)多的(de)建(jian)設,在(zai)xx開(kai)發公司及各(ge)(ge)級主管部(bu)門的(de)領導下(xia),經(jing)過各(ge)(ge)個(ge)參(can)建(jian)單(dan)位精誠配合、團結協(xie)助共同使本工(gong)程得以順利竣工(gong)。在(zai)此(ci),請允許我(wo)代表公司及監理部(bu)向(xiang)蒞臨(lin)xx擴建(jian)工(gong)程竣工(gong)驗(yan)收的(de)各(ge)(ge)位領導、專家表示衷心的(de)感謝!下(xia)面將監理工(gong)作情況作簡要總(zong)結匯(hui)報。
一、工程概況
(略)
二、監理(li)工(gong)作(zuo)概述
從xx年xx月,施工(gong)單位逐步進(jin)場施工(gong)至xx年xx月份竣(jun)工(gong)驗收(shou)(shou),根據設計及相關規(gui)范要求(qiu)對(dui)分部分項工(gong)程進(jin)行結構驗收(shou)(shou),符合要求(qiu)。
我公司對該項(xiang)目(mu)十分重視,項(xiang)目(mu)總監理(li)(li)工(gong)程(cheng)(cheng)師(shi)由(you)我公司xx擔任(ren),并(bing)抽調公司精干的(de)專業技術(shu)人員組(zu)建項(xiang)目(mu)監理(li)(li)部,編(bian)制(zhi)了(le)監理(li)(li)規劃,組(zu)織(zhi)各專業監理(li)(li)工(gong)程(cheng)(cheng)師(shi)在(zai)詳細了(le)解規范、強制(zhi)行(xing)條文、招投(tou)標文件,認真熟悉施工(gong)圖紙,在(zai)領悟設計意(yi)圖的(de)前(qian)提下,編(bian)制(zhi)了(le)具有可(ke)指導性和可(ke)操作性的(de)各專業實施細則,并(bing)在(zai)監理(li)(li)過程(cheng)(cheng)中(zhong)嚴(yan)格執行(xing)。監理(li)(li)項(xiang)目(mu)部為保(bao)障項(xiang)目(mu)實施過程(cheng)(cheng)中(zhong)高標準進(jin)行(xing)各項(xiang)質(zhi)量安全控制(zhi),實行(xing)了(le)對施工(gong)單位的(de)技術(shu)交底制(zhi)度、安全交底制(zhi)度、見(jian)證取樣制(zhi)度、工(gong)程(cheng)(cheng)驗(yan)收等一系(xi)列監理(li)(li)措(cuo)施,確(que)保(bao)了(le)工(gong)程(cheng)(cheng)監理(li)(li)工(gong)作的(de)順利開展。
三、工程(cheng)質量控制(zhi)
1、業主、監理共同(tong)組(zu)織第工(gong)地例會(hui),會(hui)議上明確了質(zhi)量目標(biao),并提出了達到(dao)該(gai)目標(biao)在(zai)質(zhi)量控制方(fang)面應注意的問題。
2、工(gong)程施(shi)(shi)工(gong)前,要(yao)求(qiu)施(shi)(shi)工(gong)單位完善和健全質量保證(zheng)體系,包(bao)括(kuo)項(xiang)目經理、技術負(fu)責(ze)人(ren)在(zai)內的質檢、資料、施(shi)(shi)工(gong)等“五員”必須到(dao)位,要(yao)求(qiu)施(shi)(shi)工(gong)單位對每一道工(gong)序加強自檢職能,經自檢合格(ge)才能通知監理工(gong)程師確認,確保了工(gong)程各工(gong)序的質量。
3、根(gen)據實際情況,編制監理(li)旁(pang)站(zhan)(zhan)計劃,對應該旁(pang)站(zhan)(zhan)的(de)重點和(he)關鍵(jian)部位如:打(da)樁、混凝(ning)土澆筑等進(jin)行(xing)全過程旁(pang)站(zhan)(zhan),并做(zuo)好相(xiang)應的(de)記錄。
4、編制見證取樣計劃(hua),嚴格按(an)照計劃(hua)執(zhi)行,本(ben)工程檢測送xx建設工程檢測有限公司的鋼筋原材(cai)、鋼筋焊(han)接、混凝(ning)土、砂漿等試件均合格。
5、嚴格把好材料進場質量關(guan),作為工(gong)程質量控(kong)制的(de)切入口,對(dui)其認真(zhen)核對(dui)產品合格證、質保單、檢測報(bao)告,并(bing)對(dui)外觀進行檢查,按規范抽取適當(dang)數量送檢,對(dui)不符合的(de)立即要(yao)求施工(gong)單位退場,不得(de)在工(gong)程中(zhong)使(shi)用。
6、加強對(dui)工(gong)程現(xian)(xian)場的平行(xing)檢查(cha)、現(xian)(xian)場巡視力度等(deng)相關監(jian)理(li)工(gong)作,發現(xian)(xian)問題(ti)立即(ji)以(yi)口頭(tou)及書面形式通(tong)知施(shi)工(gong)單(dan)(dan)位(wei)進(jin)行(xing)整(zheng)(zheng)改,對(dui)相關問題(ti)跟(gen)蹤調查(cha),直到(dao)整(zheng)(zheng)改完畢,復查(cha)合(he)格方同意進(jin)入下(xia)道工(gong)序(xu)施(shi)工(gong)。施(shi)工(gong)過程中,我監(jian)理(li)部(bu)針對(dui)施(shi)工(gong)單(dan)(dan)位(wei)下(xia)發了(le)多(duo)分監(jian)理(li)工(gong)程師通(tong)知單(dan)(dan),關于現(xian)(xian)場的質量(liang)問題(ti)和(he)施(shi)工(gong)安全問題(ti)占主要部(bu)分,施(shi)工(gong)單(dan)(dan)位(wei)基(ji)本(ben)上能按(an)設計及規范要求及時整(zheng)(zheng)改到(dao)位(wei)。
7、各(ge)工序(xu)施(shi)工過程(cheng)中(zhong),加強現(xian)場(chang)實測實量(liang)工作,對施(shi)工單位(wei)報送的(de)檢(jian)(jian)驗批等(deng)評定資料到現(xian)場(chang)對照檢(jian)(jian)查,得出(chu)實際(ji)數(shu)據,對超出(chu)規(gui)范的(de)部(bu)位(wei)進行整(zheng)改。
8、對工(gong)程材(cai)料及構配(pei)件安裝(zhuang),我監理部做(zuo)了如下工(gong)作:
(1)按(an)照各項施工(gong)驗(yan)收規范,對安(an)裝材料及每道(dao)安(an)裝工(gong)序進行嚴(yan)格監理。
(2)對完成的工(gong)序,我們(men)均按照(zhao)設計(ji)及規(gui)范要求(qiu)進行檢測(ce),對相關(guan)部位進行現場(chang)檢測(ce)或試驗,如(ru)避雷引下線接地電(dian)阻(zu)測(ce)試、等電(dian)位聯結(jie)的絕(jue)緣電(dian)阻(zu)測(ce)試等,發(fa)現問(wen)題及時要求(qiu)施工(gong)單(dan)位整改。
四、工程進度(du)控制
本工(gong)程在(zai)建設單(dan)位(wei)(wei)的(de)(de)(de)正確領(ling)導下,我(wo)監理部做了大量的(de)(de)(de)督促、協(xie)調工(gong)作,急業主之所急,在(zai)確保安全、質量的(de)(de)(de)前提下把施工(gong)進度放在(zai)關鍵位(wei)(wei)置,經過(guo)各(ge)單(dan)位(wei)(wei)的(de)(de)(de)不懈(xie)努(nu)力終于在(zai)xx年(nian)xx月份竣工(gong)。
對施工進(jin)度(du),監理在(zai)控制工程(cheng)進(jin)度(du)方面(mian)做工作(zuo)總結如下:
1、根據現場實際(ji)出現的.進度問題(ti)(ti),多次(ci)以(yi)書面或組織專題(ti)(ti)會議討論(lun)的方式施工單位合理安排,調整人力(li)、物力(li)、資金,使施工單位更能引起(qi)高度重視。
2、監理負責(ze)牽頭,協調解決對施工(gong)進度(du)產(chan)生影(ying)響的各種因素(su),并根據進度(du)計(ji)劃確定每周應該完成(cheng)的工(gong)程量。
3、在計(ji)劃(hua)工(gong)(gong)期產生(sheng)偏離(li),關鍵工(gong)(gong)序(xu)、節點(dian)無(wu)法(fa)按計(ji)劃(hua)完成時,征得(de)業主同意,要(yao)求(qiu)各參建單(dan)位及(ji)時調(diao)整施工(gong)(gong)計(ji)劃(hua),報監(jian)理部審批后實施。在裝飾階段,限(xian)定施工(gong)(gong)單(dan)位完成相應工(gong)(gong)序(xu)所需天數,確定各工(gong)(gong)序(xu)的(de)施工(gong)(gong)人數,進度(du)控制取得(de)較明(ming)顯的(de)效果。
4、根據(ju)各施工單位上報的進(jin)度計劃,監理按照現場實際情況(kuang),與(yu)業(ye)主(zhu)共(gong)同商定,確定項目達到竣(jun)工預驗收調節的終(zhong)截(jie)止日(ri)期。
5、對施工單(dan)位(wei)進度及時掌(zhang)握(wo)情況,以書面形式總結上報業主。
五、工程投資(zi)控制(zhi)
1、工程款計量
監(jian)理根據業主與各施工(gong)(gong)單位簽(qian)訂的(de)(de)施工(gong)(gong)合(he)(he)同,工(gong)(gong)程進(jin)度款嚴(yan)(yan)格按照合(he)(he)同約定節點進(jin)行(xing)(xing)簽(qian)證,對涉及變更的(de)(de)工(gong)(gong)程量嚴(yan)(yan)格按現場實(shi)際情(qing)況進(jin)行(xing)(xing)實(shi)測實(shi)量。
2、設計變更
會同建(jian)設(she)單(dan)位(wei)、設(she)計單(dan)位(wei)、施(shi)工單(dan)位(wei)對變更設(she)計進行(xing)會審后(hou),提出(chu)(chu)審查(cha)意見。對施(shi)工和設(she)計等提出(chu)(chu)的聯系單(dan)和變更,我(wo)們及時提出(chu)(chu)合(he)理化建(jian)議,征得建(jian)設(she)單(dan)位(wei)和設(she)計單(dan)位(wei)終確(que)認后(hou)通知施(shi)工單(dan)位(wei)照此執行(xing),并及時進行(xing)驗收(shou)。
六、合同管理
本工(gong)程涉及安裝工(gong)種較多,監理部對分包(bao)單位等單位的資質進(jin)行了嚴格(ge)審查(cha),對施(shi)工(gong)過程中(zhong)總、分提出的問題積極協調,使(shi)工(gong)程能夠順利進(jin)行。
七、安全文明施(shi)工
在監(jian)理過程中,監(jian)理項目部一直把(ba)安(an)全(quan)(quan)(quan)文明(ming)施工(gong)(gong)工(gong)(gong)作(zuo)(zuo)放在首要位(wei)置,時刻牢記其重要性,并(bing)嚴格督促施工(gong)(gong)單(dan)位(wei)按(an)照(zhao)安(an)全(quan)(quan)(quan)生(sheng)產法、安(an)全(quan)(quan)(quan)條(tiao)例(li)做好(hao)安(an)全(quan)(quan)(quan)文明(ming)施工(gong)(gong)工(gong)(gong)作(zuo)(zuo),對重要部位(wei)、環節存(cun)在安(an)全(quan)(quan)(quan)生(sheng)產隱(yin)患的,立即要求施工(gong)(gong)單(dan)位(wei)整改,直到消除(chu)隱(yin)患為(wei)止。
在監理(li)過(guo)程(cheng)中主要(yao)做了以下工作(zuo):
1、根據本工程特點,結合現(xian)場實際情況,工地開工前編制(zhi)《安全文明施(shi)工監(jian)理細則》,指導日常(chang)監(jian)理過(guo)程中對(dui)照檢(jian)查、實施(shi)。
2、堅(jian)持每天對工(gong)地安(an)(an)全生產、文明施工(gong)進行檢查,特(te)別是對支模架(jia)、外(wai)腳手架(jia)、井架(jia)、安(an)(an)全用電、“三寶四(si)口、五臨邊”防(fang)護等重要部位(wei)的(de)安(an)(an)全檢查,并記錄好監理臺帳,對出(chu)現的(de)安(an)(an)全隱患(huan),不(bu)符(fu)合(he)要求(qiu)的(de)立即指(zhi)出(chu),要求(qiu)施工(gong)單位(wei)整改徹底。
3、定期(qi)檢查施工單位(wei)的安(an)全臺帳,特別對職工安(an)全教育、安(an)全交底方面進(jin)行認(ren)真檢查,對存在不(bu)足之處及(ji)時提出。
4、通過監(jian)理例會(hui)、月報的形式(shi)對安全(quan)生(sheng)產文明施(shi)(shi)工提出監(jian)理意見,針對安全(quan)生(sheng)產文明施(shi)(shi)工存在的問題進行總(zong)結、分析,提出下階段的工作重(zhong)點(dian),要求施(shi)(shi)工單位引起重(zhong)視。
在建設單位的領導下,經過(guo)我監理(li)人(ren)員的嚴格督促及施工(gong)單位的配(pei)合,本(ben)工(gong)程未發生重(zhong)大安全事(shi)故(gu)。
八(ba)、質量(liang)保(bao)證(zheng)資料、分(fen)部分(fen)項評定
原材質保、試塊統計、地(di)基驗槽、沉降觀(guan)測、結構實(shi)體檢(jian)測、隱(yin)蔽驗收(shou)及(ji)分部、分項評定(ding)資料均符合驗收(shou)規定(ding)。
九、外觀評價
本工程外觀質量(liang)(liang)(liang)、截(jie)面(mian)尺寸、磚砌體截(jie)面(mian)尺寸經監(jian)理(li)現場(chang)實測(ce)實量(liang)(liang)(liang)符合規范要求,但裝修觀感質量(liang)(liang)(liang)一(yi)般(ban)。
十、工程評價
xx擴建工程符合驗收評定標準,評定合格。
十一、結束語
xx擴(kuo)建(jian)工(gong)(gong)程歷(li)經(jing)2年(nian)多時間,經(jing)過參建(jian)單位(wei)的(de)(de)(de)(de)不(bu)懈努力下(xia),用辛勞的(de)(de)(de)(de)汗水迎來(lai)了今(jin)天(tian)的(de)(de)(de)(de)竣工(gong)(gong)驗收,回顧(gu)整個工(gong)(gong)程建(jian)設(she)的(de)(de)(de)(de)每(mei)一幕,大家都有深切的(de)(de)(de)(de)感(gan)受。本工(gong)(gong)程遇(yu)到的(de)(de)(de)(de)情(qing)況較多,處理難度較大,經(jing)歷(li)了各(ge)方(fang)配合解決(jue)。但也(ye)為各(ge)參建(jian)單位(wei)提供了大顯身手的(de)(de)(de)(de)舞臺,積累了寶(bao)貴經(jing)驗,我們全體監理工(gong)(gong)作人員也(ye)學(xue)到了很(hen)多工(gong)(gong)程管(guan)理經(jing)驗,在(zai)此向xx開發公司的(de)(de)(de)(de)領導表示(shi)衷心的(de)(de)(de)(de)感(gan)謝!對質監站(zhan)、設(she)計(ji)院(yuan)(yuan)、勘察院(yuan)(yuan)等相關單位(wei)給(gei)予(yu)我們工(gong)(gong)作上的(de)(de)(de)(de)熱情(qing)指導和(he)幫助表示(shi)感(gan)謝!在(zai)今(jin)后的(de)(de)(de)(de)工(gong)(gong)作中(zhong),我們將認真總結工(gong)(gong)作經(jing)驗,在(zai)今(jin)后的(de)(de)(de)(de)工(gong)(gong)作中(zhong)更加完善(shan)。
8.2025年工程監理竣工工作總結 篇八
回首(shou)過去,展望未來,有對(dui)本(ben)年度收獲的(de)(de)(de)(de)(de)(de)喜(xi)悅,也有對(dui)未來急切(qie)的(de)(de)(de)(de)(de)(de)期(qi)望,喜(xi)悅的(de)(de)(de)(de)(de)(de)是我(wo)(wo)在領(ling)導(dao)和同事們的(de)(de)(de)(de)(de)(de)關懷幫忙下,認真學習領(ling)會公(gong)司企業文(wen)化精神,以(yi)公(gong)司服務(wu)理(li)(li)念為指導(dao),通(tong)過自身的(de)(de)(de)(de)(de)(de)不懈發(fa)奮,較好(hao)的(de)(de)(de)(de)(de)(de)完成了本(ben)職工(gong)作和領(ling)導(dao)安排的(de)(de)(de)(de)(de)(de)任務(wu);期(qi)望的(de)(de)(de)(de)(de)(de)是我(wo)(wo)深深明白在從事監理(li)(li)工(gong)作當中仍有較多的(de)(de)(de)(de)(de)(de)不足需要(yao)學習和改善,我(wo)(wo)將(jiang)總(zong)結經驗,反省自身不足,提(ti)高(gao)自己(ji)的(de)(de)(de)(de)(de)(de)監理(li)(li)業務(wu)水平,成為公(gong)司更(geng)好(hao)更(geng)快發(fa)展過程中的(de)(de)(de)(de)(de)(de)一員,現就本(ben)年度監理(li)(li)工(gong)作狀況總(zong)結如下:
一、個人年度主(zhu)要工作資料及崗(gang)位職責履行狀況(kuang)
20xx年上半年,我(wo)主要(yao)參與(yu)了xx工(gong)(gong)(gong)程現(xian)場(chang)監理(li)工(gong)(gong)(gong)作(zuo),下半年,主要(yao)參與(yu)了xx工(gong)(gong)(gong)程現(xian)場(chang)監理(li)工(gong)(gong)(gong)作(zuo)。助人(ren)為樂(le)的(de)諺語在(zai)這一年的(de)工(gong)(gong)(gong)作(zuo)中(zhong),服從(cong)領導安排,認真履行崗位職責,工(gong)(gong)(gong)作(zuo)期間(jian),我(wo)從(cong)不(bu)放松加強理(li)論和實踐的(de)研習,嚴格(ge)(ge)要(yao)求(qiu)自己,認真為建(jian)設單位熱(re)情服務,遵照(zhao)監理(li)合同(tong)要(yao)求(qiu),嚴格(ge)(ge)按(an)照(zhao)監理(li)規范及監理(li)工(gong)(gong)(gong)作(zuo)程序,履行監理(li)職責。
在(zai)施(shi)工(gong)過程中,采(cai)用旁站、巡(xun)視(shi)、平行檢驗方(fang)(fang)式進行每道(dao)工(gong)序的(de)過程控(kong)制。對現場存在(zai)的(de)質量安全問(wen)題(ti),調查研究找(zhao)出問(wen)題(ti)的(de)根源,要求(qiu)施(shi)工(gong)方(fang)(fang)采(cai)取有(you)效解(jie)決(jue)辦法將其解(jie)決(jue),全程跟蹤(zong)監督施(shi)工(gong)方(fang)(fang)落實整改(gai),杜絕類似(si)問(wen)題(ti)再次發生。
針對(dui)進(jin)場(chang)材料(liao)(高強土(tu)工格(ge)柵、土(tu)工布、柵欄板、壓(ya)腳塊、踏步(bu)料(liao)石等(deng)),按照標準(zhun)和(he)設計要求對(dui)施工方提交的(de)相關報驗資料(liao)進(jin)行核(he)查,對(dui)材料(liao)進(jin)場(chang)時進(jin)行外觀(guan)(guan)質(zhi)量(liang)檢查,對(dui)外觀(guan)(guan)質(zhi)量(liang)上不貼合要求的(de)禁止用入工程(cheng)中。
針對工(gong)(gong)(gong)(gong)程關(guan)鍵部(bu)位(wei)施(shi)工(gong)(gong)(gong)(gong)時(shi),提前到達旁(pang)站位(wei)置,檢(jian)查施(shi)工(gong)(gong)(gong)(gong)準備(bei)工(gong)(gong)(gong)(gong)作,并旁(pang)站施(shi)工(gong)(gong)(gong)(gong)全過程,及(ji)時(shi)、完全真實地作好書(shu)面(mian)的(de)旁(pang)站記錄。對要驗(yan)收的(de)隱蔽工(gong)(gong)(gong)(gong)程嚴格(ge)按照驗(yan)收規范進行(xing)(xing)驗(yan)收,如(ru)果驗(yan)收不(bu)合(he)格(ge),令其整(zheng)改直(zhi)至合(he)格(ge),才能進行(xing)(xing)下(xia)道工(gong)(gong)(gong)(gong)序(xu)施(shi)工(gong)(gong)(gong)(gong)。對各施(shi)工(gong)(gong)(gong)(gong)過程中檢(jian)查所發(fa)(fa)現的(de)問題(ti),及(ji)時(shi)采用口頭形式(shi)或書(shu)面(mian)形式(shi)通知施(shi)工(gong)(gong)(gong)(gong)單位(wei)工(gong)(gong)(gong)(gong)程項目管理部(bu),發(fa)(fa)現問題(ti)及(ji)時(shi)向(xiang)總(zong)監(jian)匯(hui)報(bao),并督促施(shi)工(gong)(gong)(gong)(gong)單位(wei)落(luo)實整(zheng)改及(ji)進行(xing)(xing)再(zai)次的(de)復核檢(jian)查。盡自己發(fa)(fa)奮(fen)做好工(gong)(gong)(gong)(gong)程建(jian)設(she)施(shi)工(gong)(gong)(gong)(gong)階段的(de)監(jian)理工(gong)(gong)(gong)(gong)作。
二、工作中的體會和感受
在監(jian)(jian)理(li)(li)工(gong)(gong)(gong)作(zuo)過(guo)程(cheng)中,我通過(guo)對監(jian)(jian)理(li)(li)理(li)(li)論的(de)(de)(de)(de)學(xue)習以及(ji)現(xian)階段監(jian)(jian)理(li)(li)行(xing)業(ye)的(de)(de)(de)(de)發展狀態的(de)(de)(de)(de)認知,深刻體(ti)會(hui)感受到作(zuo)為(wei)(wei)監(jian)(jian)理(li)(li)人員,積極(ji)主(zhu)動為(wei)(wei)建設(she)單位(wei)的(de)(de)(de)(de)'利(li)益著想,為(wei)(wei)工(gong)(gong)(gong)程(cheng)質量負責(ze),為(wei)(wei)施(shi)(shi)工(gong)(gong)(gong)人員的(de)(de)(de)(de)安全負責(ze),才(cai)是監(jian)(jian)理(li)(li)工(gong)(gong)(gong)作(zuo)的(de)(de)(de)(de)信(xin)念和(he)無窮力量。只有(you)具備較高專業(ye)技能(neng)和(he)綜合素(su)質及(ji)良好(hao)(hao)的(de)(de)(de)(de)職(zhi)業(ye)道德,才(cai)能(neng)真正(zheng)(zheng)做好(hao)(hao)監(jian)(jian)理(li)(li)的(de)(de)(de)(de)本職(zhi)工(gong)(gong)(gong)作(zuo),才(cai)能(neng)夠體(ti)現(xian)守法、誠信(xin)、公(gong)正(zheng)(zheng)、公(gong)平的(de)(de)(de)(de)執業(ye)準則。明白監(jian)(jian)理(li)(li)工(gong)(gong)(gong)作(zuo)的(de)(de)(de)(de)重(zhong)要(yao)(yao)性,樹立正(zheng)(zheng)確的(de)(de)(de)(de)監(jian)(jian)理(li)(li)工(gong)(gong)(gong)作(zuo)態度,用實事求(qiu)是的(de)(de)(de)(de)工(gong)(gong)(gong)作(zuo)態度去處理(li)(li)施(shi)(shi)工(gong)(gong)(gong)中出現(xian)的(de)(de)(de)(de)各種問題(ti),才(cai)能(neng)有(you)效地開展工(gong)(gong)(gong)作(zuo),積極(ji)主(zhu)動的(de)(de)(de)(de)運(yun)用自(zi)己(ji)專業(ye)技術及(ji)聰明才(cai)智,科學(xue)公(gong)正(zheng)(zheng)的(de)(de)(de)(de)行(xing)使監(jian)(jian)理(li)(li)權利(li)和(he)義(yi)務(wu),與(yu)施(shi)(shi)工(gong)(gong)(gong)單位(wei)搞好(hao)(hao)工(gong)(gong)(gong)作(zuo)配(pei)合,滿足建設(she)單位(wei)的(de)(de)(de)(de)要(yao)(yao)求(qiu),為(wei)(wei)業(ye)主(zhu)帶給優(you)質高效的(de)(de)(de)(de)服務(wu)。
三(san)、今(jin)后的工作(zuo)打算及個人職業(ye)發(fa)展意見
作(zuo)(zuo)為一名年輕的監理(li)工作(zuo)(zuo)者,熱愛(ai)自己(ji)的本職(zhi)工作(zuo)(zuo),有(you)良好(hao)的工作(zuo)(zuo)作(zuo)(zuo)風(feng)和吃苦耐勞精神,工作(zuo)(zuo)態度嚴禁,喜愛(ai)鉆研工程(cheng)監理(li)中出現(xian)問題產生(sheng)的原因及處理(li)方(fang)法,熱衷于(yu)對工程(cheng)問題處理(li)方(fang)案的積累。
在(zai)今后的(de)(de)工(gong)作中認真(zhen)履行自(zi)(zi)己的(de)(de)崗位職責,要嚴格按國家規范(fan)、以設(she)計(ji)圖紙為依(yi)據實(shi)施監(jian)(jian)理(li)(li)(li)工(gong)作。在(zai)工(gong)作中不(bu)(bu)(bu)斷反省自(zi)(zi)身不(bu)(bu)(bu)足,加強監(jian)(jian)理(li)(li)(li)業(ye)務學(xue)習,不(bu)(bu)(bu)斷提(ti)高自(zi)(zi)身素質,發奮(fen)做好(hao)監(jian)(jian)理(li)(li)(li)工(gong)作,加強對管(guan)理(li)(li)(li)理(li)(li)(li)論(lun)知(zhi)識的(de)(de)學(xue)習,靈活(huo)多變(bian)的(de)(de)處理(li)(li)(li)實(shi)際(ji)問題,認真(zhen)完成領導交給的(de)(de)各項工(gong)作,發奮(fen)將自(zi)(zi)己的(de)(de)專業(ye)技(ji)術(shu)水平(ping)提(ti)高到一(yi)個(ge)新的(de)(de)臺階,真(zhen)正成為一(yi)個(ge)合格的(de)(de)監(jian)(jian)理(li)(li)(li)人員。
四、對公司的(de)意見和推薦
1、推薦公司要(yao)對(dui)不(bu)一(yi)樣的員工(gong)進行有(you)針對(dui)性的專業(ye)培訓,多招聘一(yi)些有(you)職(zhi)業(ye)資格證書又能獨當一(yi)面的人才開展工(gong)作。
2、推薦公司(si)組(zu)(zu)織具有(you)良好公關潛質的人才,并組(zu)(zu)建成相關部門(men),應對監理行業的社會化(hua)、監理招(zhao)投標(biao)的公開化(hua)、復合化(hua)。
五、結束語
公司領導的(de)(de)關(guan)心(xin)支(zhi)持(chi)及工作條件(jian)的(de)(de)舒適給(gei)了我(wo)發奮工作的(de)(de)動力,同事間的(de)(de)熱情關(guan)懷及協作互助給(gei)了我(wo)工作的(de)(de)舒暢感和踏實感,公司特(te)有的(de)(de)企業文化氛圍給(gei)了我(wo)工作的(de)(de)信(xin)心(xin)。我(wo)堅信(xin)自(zi)己能夠在(zai)今后的(de)(de)工作中做(zuo)的(de)(de)更好(hao),為公司的(de)(de)發展貢(gong)獻自(zi)己的(de)(de)一份力量。
9.2025年工程監理竣工工作總結 篇九
xx市克孜加爾水(shui)庫工(gong)程建設征(zheng)地(di)移民安置點生活(huo)區基(ji)礎設施項(xiang)目,總(zong)投資額602萬元,棚圈、伙(huo)房為磚木結構;水(shui)泥(ni)(ni)砂(sha)漿抹面(mian)(mian)(mian);方木檁(lin)條(tiao);草泥(ni)(ni)屋面(mian)(mian)(mian);塑鋼窗(chuang);木門。伙(huo)房為防盜門;室(shi)內砼水(shui)泥(ni)(ni)地(di)面(mian)(mian)(mian);墻(qiang)面(mian)(mian)(mian)內外涂刷(shua)(shua)乳膠(jiao)漆;屋面(mian)(mian)(mian)3+3SBS防水(shui)層。大房外墻(qiang)涂刷(shua)(shua)乳膠(jiao)漆;室(shi)外砼水(shui)泥(ni)(ni)地(di)面(mian)(mian)(mian)。自(zi)20xx年8月13日開工(gong),至20xx年9月11日竣(jun)工(gong),交付使用(yong),共30天(日歷天)。
項目監理:
xx工程管理(li)(li)咨(zi)詢公司(si)受xx市克(ke)(ke)孜加(jia)水庫(ku)(ku)工程建(jian)設管理(li)(li)處的(de)委托,承接了xxx市克(ke)(ke)孜加(jia)爾水庫(ku)(ku)工程建(jian)設征(zheng)地(di)移(yi)民(min)安置點(dian)生(sheng)活區基礎設施項(xiang)目的(de)監理(li)(li)工作,對(dui)該工程的(de)施工階(jie)段(duan)進行監理(li)(li)。
項(xiang)(xiang)(xiang)目(mu)(mu)(mu)監(jian)(jian)(jian)(jian)理(li)合同(tong)簽訂后,我(wo)公(gong)司立即組建(jian)(jian)了(le)監(jian)(jian)(jian)(jian)理(li)組進(jin)駐用(yong)戶(hu)(hu)現場,在(zai)總監(jian)(jian)(jian)(jian)理(li)工(gong)(gong)(gong)程(cheng)(cheng)(cheng)師(shi)的(de)(de)統(tong)一組織和安排下,按照監(jian)(jian)(jian)(jian)理(li)程(cheng)(cheng)(cheng)序開展監(jian)(jian)(jian)(jian)理(li)工(gong)(gong)(gong)作。在(zai)項(xiang)(xiang)(xiang)目(mu)(mu)(mu)建(jian)(jian)設(she)施(shi)工(gong)(gong)(gong)階段,依據信息系統(tong)過程(cheng)(cheng)(cheng)監(jian)(jian)(jian)(jian)理(li)有關的(de)(de)國家政策、法(fa)律、法(fa)規、標(biao)準、規范,信息技術(shu)國家標(biao)準,建(jian)(jian)設(she)單(dan)(dan)位(wei)(wei)與承建(jian)(jian)單(dan)(dan)位(wei)(wei)簽訂的(de)(de)項(xiang)(xiang)(xiang)目(mu)(mu)(mu)建(jian)(jian)設(she)合同(tong)、相關資(zi)料,建(jian)(jian)設(she)單(dan)(dan)位(wei)(wei)與監(jian)(jian)(jian)(jian)理(li)單(dan)(dan)位(wei)(wei)簽訂的(de)(de)監(jian)(jian)(jian)(jian)理(li)合同(tong)對工(gong)(gong)(gong)程(cheng)(cheng)(cheng)的(de)(de)質量、進(jin)度、投資(zi)進(jin)行(xing)控制,對項(xiang)(xiang)(xiang)目(mu)(mu)(mu)的(de)(de)合同(tong)和信息文檔資(zi)料進(jin)行(xing)管理(li)。定期召(zhao)開監(jian)(jian)(jian)(jian)理(li)例會,檢查各項(xiang)(xiang)(xiang)工(gong)(gong)(gong)作的(de)(de)完成情況,協(xie)調解決存在(zai)的(de)(de)問(wen)題;不定期的(de)(de)向用(yong)戶(hu)(hu)提交階段總結;及(ji)時把握項(xiang)(xiang)(xiang)目(mu)(mu)(mu)存在(zai)的(de)(de)問(wen)題并(bing)提出(chu)監(jian)(jian)(jian)(jian)理(li)建(jian)(jian)議;公(gong)平公(gong)正地協(xie)調處理(li)項(xiang)(xiang)(xiang)目(mu)(mu)(mu)實施(shi)中(zhong)遇到的(de)(de)問(wen)題,確保了(le)工(gong)(gong)(gong)程(cheng)(cheng)(cheng)建(jian)(jian)設(she)的(de)(de)質量和順利進(jin)行(xing)。項(xiang)(xiang)(xiang)目(mu)(mu)(mu)監(jian)(jian)(jian)(jian)理(li)部全面(mian)履行(xing)了(le)監(jian)(jian)(jian)(jian)理(li)委托合同(tong)賦予的(de)(de)義務和責任(ren),圓滿完成了(le)本(ben)工(gong)(gong)(gong)程(cheng)(cheng)(cheng)的(de)(de)監(jian)(jian)(jian)(jian)理(li)任(ren)務,監(jian)(jian)(jian)(jian)理(li)工(gong)(gong)(gong)作控制目(mu)(mu)(mu)標(biao)達到合同(tong)要求。
(一)基本做法
在(zai)依據建筑工程監理規(gui)范及有(you)關規(gui)定和本公(gong)司監理經驗的基礎上,結合本工程的實際(ji)情況,確立了(le)對本工程進行監理的基本做(zuo)法:
1、統(tong)一(yi)思想、理順關(guan)系(xi)、確立統(tong)一(yi)的(de)管(guan)理與(yu)監理體(ti)制。
2、建立監理組(zu)織機(ji)構。
3、監理組(zu)內部建立崗位責任制,并建立了例會和月(yue)度(du)報(bao)告(gao)制度(du)。
(二)質量(liang)控(kong)制(zhi)質量(liang)控(kong)制(zhi)的體(ti)系為:
(1)承包人自檢;(2)監理人員抽驗;(3)監理公(gong)司檢查組定期組織檢查。
質(zhi)(zhi)量(liang)(liang)控制是(shi)從原材(cai)料的(de)質(zhi)(zhi)量(liang)(liang)抓起(qi),對每(mei)道施工工序嚴密把關,監(jian)理人員旁站監(jian)督(du),使工程(cheng)質(zhi)(zhi)量(liang)(liang)較以往有(you)顯著(zhu)提(ti)高(gao)。從歷次質(zhi)(zhi)量(liang)(liang)檢(jian)查的(de)情況來看,質(zhi)(zhi)量(liang)(liang)呈(cheng)逐步提(ti)高(gao),沒有(you)發現(xian)不合(he)格(ge)(ge)的(de)計(ji)量(liang)(liang)工程(cheng)。當然,各分項(xiang)分部工程(cheng)的(de)質(zhi)(zhi)量(liang)(liang)情況是(shi)不平衡(heng)的(de),但只要發現(xian)有(you)不合(he)格(ge)(ge)工程(cheng),就(jiu)堅(jian)決(jue)推倒重(zhong)來,從而(er)保證了(le)工程(cheng)的(de)整(zheng)體質(zhi)(zhi)量(liang)(liang)。
(三)進度控制
首先對施(shi)工(gong)進度計劃進行(xing)嚴(yan)格管理(li),層層對照檢查,發現(xian)薄(bo)弱(ruo)環節(jie),即從材料、人(ren)員(yuan)及(ji)設(she)備使用計劃與實際執行(xing)情況找原因(yin),以書(shu)面(mian)形式要求(qiu)承包人(ren)采(cai)取(qu)措施(shi)。工(gong)程進度若嚴(yan)重滯(zhi)后則及(ji)時報(bao)告業主果斷(duan)決策,由業主發出(chu)書(shu)面(mian)通知收回部分工(gong)程項目,另擇施(shi)工(gong)隊(dui)伍進場施(shi)工(gong),當然,這種情況盡(jin)可(ke)能避免發生。由于及(ji)時掌握(wo)進度情況,就有了高度的.主動權。
(四)投資控制
xxx市克孜加爾水庫工(gong)程建設(she)征(zheng)地(di)移民安置點生活(huo)區(qu)基礎設(she)施(shi)項目的(de)所有(you)分項工(gong)程施(shi)工(gong)完成后,必須經過監(jian)理人(ren)員的(de)復(fu)核(he)工(gong)程量,確認無誤后,然后才同(tong)意提交建設(she)單位(wei)支(zhi)付(fu),在進度(du)款(kuan)支(zhi)付(fu)過程中都實施(shi)監(jian)督,對(dui)有(you)效控制(zhi)投資起到很大的(de)作(zuo)用。
(五)安(an)全(quan)生產控制
xxx市克孜加爾水庫工(gong)程(cheng)(cheng)建設(she)(she)(she)征地移民安(an)(an)置點生(sheng)活區基礎設(she)(she)(she)施(shi)項目(mu)在實施(shi)安(an)(an)全(quan)生(sheng)產控(kong)制(zhi)當中,監理單(dan)(dan)位依照(zhao)(zhao)有(you)關法律、法規(gui)和(he)工(gong)程(cheng)(cheng)建設(she)(she)(she)強制(zhi)性標(biao)準實施(shi)監理,建立健(jian)全(quan)安(an)(an)全(quan)生(sheng)產責任制(zhi)度,審查施(shi)工(gong)組織設(she)(she)(she)計中的安(an)(an)全(quan)技術措施(shi)或者專項施(shi)工(gong)方案是否符合(he)工(gong)程(cheng)(cheng)建設(she)(she)(she)強制(zhi)性標(biao)準,發(fa)現(xian)工(gong)程(cheng)(cheng)存在安(an)(an)全(quan)事故(gu)隱患,及(ji)時以(yi)書(shu)面形式要求施(shi)工(gong)單(dan)(dan)位整改,情況嚴重者,要求施(shi)工(gong)單(dan)(dan)位暫時停止施(shi)工(gong),并(bing)及(ji)時報告建設(she)(she)(she)單(dan)(dan)位。若施(shi)工(gong)單(dan)(dan)位拒不整改,依照(zhao)(zhao)有(you)關程(cheng)(cheng)序(xu)向有(you)關主管部門報告,當然,這種情況沒有(you)發(fa)生(sheng)在本工(gong)程(cheng)(cheng)上。由(you)于監理單(dan)(dan)位掌握了(le)安(an)(an)全(quan)生(sheng)產控(kong)制(zhi)的主動(dong)權,并(bing)層(ceng)層(ceng)責任落實安(an)(an)全(quan)生(sheng)產監控(kong),所以(yi),本工(gong)程(cheng)(cheng)的安(an)(an)全(quan)生(sheng)產情況良好(hao)。
(六)監理工作的體會
經過30天的監(jian)理實踐,不僅使(shi)我(wo)們(men)(men)自己發(fa)現了(le)(le)一些(xie)問題,同時使(shi)我(wo)們(men)(men)獲得了(le)(le)一些(xie)經驗與(yu)教訓(xun),體(ti)會如下:
要做好監理工(gong)作(zuo),必須具備(bei)三個條件:
(1)業主或(huo)建設單位的支持(chi)和信任。
(2)施工單位的配合。
(3)監(jian)理人(ren)員自身業務能力(li)的提高,不僅要有(you)較(jiao)熟練(lian)的技術(shu)、業務素(su)(su)質,還須有(you)良好(hao)的思想(xiang)品德、作風和政治素(su)(su)質,更新概念,強化管(guan)理,以盡快適應全面實施建設監(jian)理的需要。
結束語
監(jian)理(li)方在(zai)監(jian)理(li)工作(zuo)過程中,得到了建(jian)設(she)單(dan)位領導的大(da)力支持,承建(jian)單(dan)位的相(xiang)互協(xie)作(zuo)和配合。在(zai)此,本人謹(jin)代表阿(a)勒泰市克孜加爾水庫工程建(jian)設(she)征地(di)移民安置點生活區基礎設(she)施(shi)項目(mu)監(jian)理(li)部的所(suo)有成員對你們(men)的支持和配合表示衷心的感謝!
10.2025年工程監理竣工工作總結 篇十
xx工程經(jing)各參建單位的共同(tong)努力(li),順(shun)利完工。在此,我代表xx公司xx監理項目部,將本工程監理工作情況,總結如下:
一、工程概況
xx工程(cheng),由(you)xx公(gong)司承包施工。該工程(cheng)位于原xx內,為框(kuang)架結構(gou),其(qi)中:教(jiao)學樓(lou)為四層,學生公(gong)寓樓(lou)為四層,學生食堂(tang)為一層,各建筑物屋面(mian)均為陶瓷瓦坡(po)屋面(mian),總建筑面(mian)積(ji)xx,總造價為xx萬元。
二、監(jian)理(li)組織機構
我司根(gen)據監(jian)(jian)(jian)理合同和監(jian)(jian)(jian)理大綱,結合本工(gong)(gong)程具體情況,組(zu)建由總監(jian)(jian)(jian)理工(gong)(gong)程師(shi)xx,土建監(jian)(jian)(jian)理工(gong)(gong)程師(shi)xx,水電(dian)監(jian)(jian)(jian)理工(gong)(gong)程師(shi)xx組(zu)成的(de)項(xiang)目監(jian)(jian)(jian)理機(ji)構于xx年xx月(yue)xx日(ri)進場,對本工(gong)(gong)程進行監(jian)(jian)(jian)理。項(xiang)目監(jian)(jian)(jian)理組(zu)嚴格執(zhi)行監(jian)(jian)(jian)理程序,堅持(chi)“誠信、守法、公正、科學”的(de)宗旨,以“認真、嚴謹、一絲不茍”的(de)工(gong)(gong)作作風實(shi)施監(jian)(jian)(jian)理,完成了監(jian)(jian)(jian)理任務(wu)。
三、監理工作情況
1、抓(zhua)好事(shi)前控(kong)制,嚴把開(kai)工關。
在整個監理(li)過程中,我們堅持以事前(qian)控制(zhi)和主動控制(zhi)為主,依據合(he)同和設(she)計文(wen)件編制(zhi)了監理(li)規劃(hua),制(zhi)訂了具體(ti)的(de)監理(li)工作程序,明確(que)了工作內容,行(xing)為主體(ti),驗收標準及工作要求。
本工(gong)程(cheng)開工(gong)前,依(yi)據監理規(gui)范要(yao)求(qiu),我(wo)們審(shen)查了施(shi)工(gong)單位(wei)的(de)資質,現場質量(liang)管理、技術管理組(zu)織(zhi)機構、人員、制度及特殊工(gong)種(zhong)操作人員的(de)資格、上崗證(zheng)等(deng)。依(yi)據承包(bao)單位(wei)報送的(de)施(shi)工(gong)組(zu)織(zhi)設(she)計方案報審(shen)表,對施(shi)工(gong)組(zu)織(zhi)設(she)計進(jin)行了審(shen)查,并相應編制了《監理規(gui)劃》對工(gong)程(cheng)的(de)測量(liang)、定位(wei)放線,包(bao)括軸線尺寸、水平標高(gao)進(jin)行了現場復核,進(jin)一步明確了監理目標和要(yao)求(qiu),為監理工(gong)作的(de)順利開展創造了條(tiao)件。
2、嚴把原材料、半(ban)成(cheng)品(pin)進(jin)場關。
凡是進(jin)場(chang)(chang)原材(cai)(cai)料、半成(cheng)品首先要(yao)進(jin)行書面檢查,即查驗合(he)格(ge)證、準用(yong)證、質保(bao)單等,符合(he)要(yao)求后進(jin)行外(wai)觀檢查,沒有異常情(qing)況后監理見證取樣送市檢測(ce)中心復檢,做到材(cai)(cai)料進(jin)場(chang)(chang)先復檢后使用(yong),不合(he)格(ge)的(de)(de)材(cai)(cai)料拒絕用(yong)于工(gong)程上。本(ben)工(gong)程建筑材(cai)(cai)料合(he)格(ge)證、質保(bao)單齊全,對(dui)鋼材(cai)(cai)、水泥、石子、黃沙等主要(yao)建筑結(jie)構性材(cai)(cai)料都進(jin)行了(le)進(jin)場(chang)(chang)后的(de)(de)抽(chou)檢復驗,全部達(da)到合(he)格(ge)要(yao)求。
3、嚴格工序檢查,強化過程控制。
在施(shi)(shi)工(gong)監(jian)督(du)過程中,強化了(le)施(shi)(shi)工(gong)工(gong)序(xu)報驗(yan)手段,做到(dao)先報驗(yan)后施(shi)(shi)工(gong),上道工(gong)序(xu)未(wei)經驗(yan)收(shou)不得進入(ru)下(xia)道工(gong)序(xu)的施(shi)(shi)工(gong),對(dui)隱蔽工(gong)程的驗(yan)收(shou)我們項目監(jian)理部尤(you)其重視,現(xian)場(chang)監(jian)理人(ren)員對(dui)重點、關(guan)鍵(jian)部位進行了(le)旁站監(jian)督(du),如現(xian)澆鋼筋(jin)砼、梁(liang)、板、梯(ti)、屋(wu)面等。
施(shi)(shi)工(gong)中(zhong),我(wo)(wo)們(men)(men)對鋼(gang)筋(jin)砼工(gong)程,特別是(shi)(shi)(shi)樓面工(gong)程的(de)(de)施(shi)(shi)工(gong)質(zhi)量(liang)(liang)給予了(le)(le)高度(du)的(de)(de)重視(shi)和嚴格(ge)的(de)(de)控制(zhi)(zhi),在整(zheng)個(ge)施(shi)(shi)工(gong)過(guo)程中(zhong),我(wo)(wo)們(men)(men)把(ba)鋼(gang)筋(jin)的(de)(de)`綁扎制(zhi)(zhi)作質(zhi)量(liang)(liang),板的(de)(de)澆筑(zhu)厚度(du)、砼的(de)(de)配合比、坍(tan)落(luo)度(du)和養護等方(fang)面作為重點來控制(zhi)(zhi),以確保砼的(de)(de)施(shi)(shi)工(gong)質(zhi)量(liang)(liang)。在墻(qiang)體施(shi)(shi)工(gong)中(zhong),我(wo)(wo)們(men)(men)抓(zhua)了(le)(le)以下關(guan)鍵(jian):一是(shi)(shi)(shi)磚的(de)(de)濕水(shui);二是(shi)(shi)(shi)砂漿的(de)(de)正確拌制(zhi)(zhi);三是(shi)(shi)(shi)砌筑(zhu)的(de)(de)質(zhi)量(liang)(liang),其中(zhong)砂漿的(de)(de)飽滿(man)度(du)、粘結度(du)、垂直(zhi)平(ping)整(zheng)度(du)及拉結筋(jin)的(de)(de)設置作為關(guan)鍵(jian)來監督。
在監(jian)(jian)理工(gong)作過程(cheng)(cheng)中,共發出監(jian)(jian)理工(gong)作聯系單(dan)9份,監(jian)(jian)理工(gong)程(cheng)(cheng)師(shi)通(tong)知單(dan)33份,安全(quan)隱患整改通(tong)知單(dan)3份,在工(gong)程(cheng)(cheng)實施(shi)過程(cheng)(cheng)中針對工(gong)程(cheng)(cheng)質(zhi)量(liang)、造價、進度、安全(quan)、合同(tong)管(guan)理等(deng)事宜(yi)每周召開(kai)工(gong)地(di)例(li)(li)會,并根據工(gong)程(cheng)(cheng)實際情(qing)況召開(kai)專題工(gong)地(di)例(li)(li)會12次。
4、加強(qiang)事(shi)后控制,確(que)保(bao)施工質量符合(he)合(he)同要求(qiu)。
(1)本工(gong)程(cheng)在施工(gong)全(quan)過(guo)程(cheng)中沒有發生質量(liang)事故,作為(wei)一般性質量(liang)問題(ti),施工(gong)單位(wei)(wei)通過(guo)自查(cha)、自檢后內部整(zheng)改;另一方面,通過(guo)監理檢查(cha)發現后通知施工(gong)單位(wei)(wei)整(zheng)改。
(2)及時督促施(shi)工單位(wei)收(shou)集整理好各(ge)種工程資料(liao),并認真(zhen)做(zuo)好自己的監理資料(liao)。
(3)要(yao)求施工(gong)單(dan)位做好(hao)已(yi)完(wan)工(gong)程的成品保護工(gong)作。
5、工(gong)程進度控制:
工(gong)(gong)(gong)程進(jin)(jin)度(du)的快(kuai)慢直接關系到工(gong)(gong)(gong)程建(jian)設項目能否按期(qi)竣工(gong)(gong)(gong)和投入使用問題。我監理組首先(xian)審(shen)查施(shi)工(gong)(gong)(gong)單位總進(jin)(jin)度(du)計(ji)(ji)(ji)劃(hua)(hua),并報業(ye)主(zhu)審(shen)核同意后,督促施(shi)工(gong)(gong)(gong)單位嚴格按照總進(jin)(jin)度(du)計(ji)(ji)(ji)劃(hua)(hua)施(shi)工(gong)(gong)(gong)。并根據總進(jin)(jin)度(du)計(ji)(ji)(ji)劃(hua)(hua)編制月(yue)進(jin)(jin)度(du)計(ji)(ji)(ji)劃(hua)(hua),一旦發現偏差,及時(shi)要求施(shi)工(gong)(gong)(gong)單位適(shi)當調整勞動力(li)、材料、設備、資金,確保(bao)工(gong)(gong)(gong)程按計(ji)(ji)(ji)劃(hua)(hua)進(jin)(jin)度(du)完成(cheng)。
6、投資控制:
項目監(jian)理部按照施工(gong)合同、工(gong)程施工(gong)實際進(jin)度(du)、工(gong)程質量對(dui)所(suo)監(jian)理工(gong)程進(jin)行工(gong)程款支付控制。
7、安全(quan)生產(chan)及(ji)文(wen)明施(shi)工:
“安(an)(an)(an)全(quan)第一,預防為主”,在監(jian)理過(guo)程(cheng)中(zhong),項目監(jian)理組始終把安(an)(an)(an)全(quan)監(jian)理作為工(gong)(gong)(gong)作重點,貫穿于(yu)監(jian)理工(gong)(gong)(gong)作的(de)全(quan)過(guo)程(cheng)。并參加了長(chang)沙(sha)縣建(jian)(jian)設局組織(zhi)召開的(de)建(jian)(jian)設工(gong)(gong)(gong)程(cheng)安(an)(an)(an)全(quan)監(jian)理工(gong)(gong)(gong)作研討___班。結合工(gong)(gong)(gong)程(cheng)實際情況,督促施(shi)工(gong)(gong)(gong)單位建(jian)(jian)立安(an)(an)(an)全(quan)生(sheng)產(chan)責任制,做好安(an)(an)(an)全(quan)生(sheng)產(chan)、文明施(shi)工(gong)(gong)(gong)教育,定時(shi)組織(zhi)施(shi)工(gong)(gong)(gong)單位進行安(an)(an)(an)全(quan)生(sheng)產(chan)檢(jian)查查,對存在的(de)安(an)(an)(an)全(quan)隱患,及時(shi)發文要求施(shi)工(gong)(gong)(gong)單位限期整改(gai)。本工(gong)(gong)(gong)程(cheng)施(shi)工(gong)(gong)(gong)過(guo)程(cheng)中(zhong)未(wei)發生(sheng)安(an)(an)(an)全(quan)事(shi)故。
通(tong)過建設(she)單(dan)位、設(she)計(ji)單(dan)位、承(cheng)包單(dan)位、監理(li)單(dan)位的共同努力,在政(zheng)府相關部門的指導和監督下,該工(gong)程(cheng)已基本按(an)合(he)同完成(cheng)。工(gong)程(cheng)技(ji)術(shu)資料(liao)已按(an)要(yao)求(qiu)整理(li),工(gong)程(cheng)質量滿足設(she)計(ji)、規范及使用功能要(yao)求(qiu)。預祝平武古城中學災后重建工(gong)程(cheng)順利通(tong)過驗收。
11.2025年工程監理竣工工作總結 篇十一
首先誠心感謝質監站領導能在(zai)百忙之中抽出時間(jian)參與此(ci)次竣(jun)工(gong)驗收(shou)。xxx工(gong)程,在(zai)相關(guan)(guan)(guan)部門領導的(de)大力(li)支持、協作和關(guan)(guan)(guan)懷下,通過勘(kan)察(cha)、設(she)(she)計(ji)(ji)、監理、施工(gong)、質監和建(jian)設(she)(she)單(dan)(dan)位(wei)各(ge)方人(ren)員的(de)共同努力(li)下,經過緊急的(de)施工(gong)建(jian)設(she)(she),已(yi)完成合同商定(ding)(ding)的(de)各(ge)項(xiang)任(ren)務。施工(gong)單(dan)(dan)位(wei)提出竣(jun)工(gong)報(bao)(bao)告(gao),并經總監簽署(shu)看法;監理單(dan)(dan)位(wei)已(yi)組(zu)織并通過了(le)預(yu)驗收(shou),并提出了(le)工(gong)程質量(liang)評估報(bao)(bao)告(gao);勘(kan)察(cha)、設(she)(she)計(ji)(ji)單(dan)(dan)位(wei)分別提出了(le)勘(kan)察(cha)、設(she)(she)計(ji)(ji)質量(liang)檢查報(bao)(bao)告(gao);我(wo)公司已(yi)按合同商定(ding)(ding)支付工(gong)程款,已(yi)與施工(gong)單(dan)(dan)位(wei)簽署(shu)工(gong)程質量(liang)保修書。本工(gong)程各(ge)項(xiang)報(bao)(bao)批資(zi)(zi)料及項(xiang)目(mu)批準相關(guan)(guan)(guan)資(zi)(zi)料、手續齊全。我(wo)就(jiu)本工(gong)程建(jian)設(she)(she)狀況(kuang)向各(ge)位(wei)領導匯報(bao)(bao)如下:
一(yi)、工程(cheng)基本(ben)狀(zhuang)況及建設程(cheng)序管(guan)理狀(zhuang)況
1、合同托(tuo)付(fu)(fu)江蘇xx建筑(zhu)(zhu)(zhu)(zhu)設(she)計有限公(gong)司(si)進(jin)行勘察(cha),托(tuo)付(fu)(fu)中國建筑(zhu)(zhu)(zhu)(zhu)xx公(gong)司(si)進(jin)行設(she)計,托(tuo)付(fu)(fu)徐州xx有限公(gong)司(si)進(jin)行監理(li),xx建筑(zhu)(zhu)(zhu)(zhu)安裝工程有限公(gong)司(si)施工。建筑(zhu)(zhu)(zhu)(zhu)師(shi):xx。
2、本工(gong)程(cheng)建筑面積6750平方米,框架6層,于20xx年(nian)10月開工(gong)-20xx年(nian)2月竣工(gong)。
二、建設管理機(ji)構狀(zhuang)況
1、我(wo)公司為保證(zheng)該工(gong)程的(de)(de)順當(dang)進行,本著質量(liang)第一、平(ping)安(an)第一和厲行節(jie)儉的(de)(de)原(yuan)則,明確了工(gong)程管理(li)的(de)(de)相關規(gui)定,其中包(bao)括廉(lian)政、質量(liang)、平(ping)安(an)、資金使(shi)用(yong)及現(xian)場施(shi)工(gong)管理(li)保證(zheng)措施(shi)。
2、施(shi)工(gong)單(dan)位實(shi)行項目經(jing)理和(he)主要(yao)技(ji)術(shu)人(ren)員負責制,各(ge)類人(ren)員職(zhi)責明確,規(gui)章制度健全,工(gong)地管理有(you)序,工(gong)程秩序良好(hao)。
三(san)、對(dui)工(gong)程設計、監理、施工(gong)單位(wei)的評價
1、設計單位(wei)能夠仔細(xi)負責(ze)地參(can)與(yu)地基驗槽;參(can)與(yu)基礎及有關重要部(bu)位(wei)工(gong)程(cheng)質量驗收(shou)(shou);參(can)與(yu)工(gong)程(cheng)竣工(gong)驗收(shou)(shou);簽發設計修(xiu)轉變(bian)更,技術洽(qia)商通知(zhi);參(can)與(yu)有關工(gong)程(cheng)質量問題(ti)的(de)處(chu)理狀況;出(chu)具設計單位(wei)工(gong)程(cheng)質量檢查報告;完成合同所商定的(de)`其它內容,良(liang)好的(de)履行了設計單位(wei)的(de)職責(ze)。
2、監(jian)理(li)(li)單位(wei)項目管理(li)(li)機構的(de)人(ren)員資格、配(pei)備及到位(wei)符合(he)要(yao)求;監(jian)理(li)(li)規劃(hua)、監(jian)理(li)(li)實(shi)施細(xi)則按規定編(bian)制、審(shen)批;對(dui)材料、構配(pei)件、設備投入(ru)使用或安裝(zhuang)前進行審(shen)查;實(shi)施見證取樣(yang)制度;對(dui)重(zhong)點部(bu)位(wei)、關鍵工序實(shi)施旁站監(jian)理(li)(li),確保(bao)質(zhi)量(liang);簽發質(zhi)量(liang)問題(ti)通知單,并復查質(zhi)量(liang)問題(ti)整(zheng)改(gai)結果;組織工序、部(bu)位(wei)的(de)質(zhi)量(liang)驗(yan)收(shou),參加單位(wei)工程質(zhi)量(liang)的(de)驗(yan)收(shou);收(shou)集(ji)整(zheng)理(li)(li)完(wan)成的(de)監(jian)理(li)(li)資料,審(shen)查、監(jian)督施工單位(wei)的(de)資料報驗(yan);出具監(jian)理(li)(li)單位(wei)工程質(zhi)量(liang)評(ping)估報告(gao);完(wan)成合(he)同所(suo)商定的(de)其(qi)它內(nei)容,履約(yue)狀(zhuang)況良好。
3、施(shi)(shi)工(gong)單(dan)位項目經理部(bu)管理人員(yuan)的(de)資格、配(pei)備(bei)到位,主要專業工(gong)種(zhong)操作上崗資格、配(pei)備(bei)及到位符合要求;施(shi)(shi)工(gong)組織設計(ji)或施(shi)(shi)工(gong)方案有(you)審批(pi)并執行;施(shi)(shi)工(gong)現(xian)場配(pei)置(zhi)施(shi)(shi)工(gong)操作技術(shu)規程(cheng)及國(guo)家(jia)有(you)關規范、標準(zhun)(zhun);按工(gong)程(cheng)技術(shu)標準(zhun)(zhun)及施(shi)(shi)工(gong)圖文件實施(shi)(shi);工(gong)序、部(bu)位、單(dan)位工(gong)程(cheng)質(zhi)(zhi)量(liang)的(de)檢驗(yan)評(ping)定(ding)符合要求;準(zhun)(zhun)時整改質(zhi)(zhi)量(liang)問題(ti)和質(zhi)(zhi)量(liang)事(shi)故的(de)處理;收集、整理完整的(de)質(zhi)(zhi)保資料;出(chu)具施(shi)(shi)工(gong)單(dan)位工(gong)程(cheng)質(zhi)(zhi)量(liang)自評(ping)報告(gao);完成合同(tong)所商定(ding)的(de)其它內容,較好(hao)的(de)履行了自己的(de)責任和義務。
四、工程造價管理狀況
本工(gong)(gong)程合同價509.40萬元,加(jia)上設(she)計(ji)變(bian)更增減賬(zhang),竣工(gong)(gong)驗收合格(ge)后,扣除保修金,由建設(she)單(dan)位與施(shi)工(gong)(gong)單(dan)位以此結清(qing),目前(qian)工(gong)(gong)程結算(suan)工(gong)(gong)作正在審(shen)核、審(shen)計(ji)之中。
五、質量(liang)管理(li)狀況
1、本工(gong)程由(you)xx市建筑工(gong)程質量監督站(zhan)進行(xing)質量監督。
2、工程所用主(zhu)要(yao)建筑材(cai)料(liao)、各(ge)種構(gou)配件及設備均有合(he)(he)格證,按規(gui)范要(yao)求進(jin)行(xing)各(ge)種檢(jian)測試(shi)驗,其(qi)檢(jian)測報告(gao)結果均合(he)(he)格。其(qi)中用于承重結構(gou)的混凝土(tu)試(shi)件、砂漿(jiang)試(shi)塊進(jin)行(xing)了見證取樣檢(jian)測,檢(jian)測數量符(fu)合(he)(he)要(yao)求。
3、本工(gong)程未發生任何質(zhi)量事(shi)故和其他事(shi)故,基(ji)礎、主體、屋面(mian)施(shi)工(gong)質(zhi)量均符合(he)規范及設計要求,有防水要求的屋面(mian)、露臺無滲漏現象。
六(liu)、平安文明施工(gong)及建設工(gong)期管(guan)理(li)狀況(kuang)
本工程(cheng)平安文(wen)明(ming)施(shi)(shi)(shi)工管理狀況:本工程(cheng)位(wei)于市中心(xin),為不影響周邊單(dan)位(wei)辦(ban)公、生(sheng)活及避開擔心(xin)全隱患的發生(sheng)。施(shi)(shi)(shi)工單(dan)位(wei)做到(dao)現場掛出平安文(wen)明(ming)施(shi)(shi)(shi)工細則及施(shi)(shi)(shi)工警告語牌(pai)子,并派專人負(fu)責文(wen)明(ming)施(shi)(shi)(shi)工管理。
七、工程檔案管理狀況施工過程中(zhong)
施工(gong)單(dan)位按《建筑工(gong)程資料(liao)管理(li)規(gui)程》,設(she)(she)專人(ren)對(dui)(dui)施工(gong)過程的全(quan)部資料(liao)進(jin)(jin)行記錄、收集和整理(li),建設(she)(she)單(dan)位親密協作。隨著工(gong)程的進(jin)(jin)展,雙方共同對(dui)(dui)資料(liao)進(jin)(jin)行檢查、核對(dui)(dui)和確認(ren)。目(mu)前,施工(gong)資料(liao)齊全(quan),竣工(gong)資料(liao)也已通(tong)過質(zhi)量監督(du)部門(men)的檢查,辦理(li)移交。
八、竣工驗收(shou)結論
本工程已于20xx年1月28日組(zu)織業(ye)主進行(xing)分戶驗收,業(ye)主評價較好,并經監理、施工、建(jian)設單位及物業(ye)單位有關人員共(gong)同預(yu)驗收,初步認為該工程建(jian)設基本符合(he)設計(ji)及規(gui)范要求(qiu),敬請xx及各位領導予以指正(zheng)。感謝!預(yu)祝此(ci)次驗收能夠圓滿勝(sheng)利。
12.2025年工程監理竣工工作總結 篇十二
由我公司承建(jian)的(de)高唐縣谷官屯村段(duan)、洼里(li)至十五里(li)鋪段(duan)、和諧王至105國道改建(jian)工程(以下(xia)簡稱:L1合同(tong)段(duan)),在業(ye)主、設(she)計(ji)院(yuan)及(ji)監理單位(wei)等部(bu)門的(de)大力支(zhi)持和關心(xin)下(xia),經過本公司全體參(can)與人員的(de)`努力,終保質保量完成了(le)施工任務(wu),交出(chu)了(le)一條優質的(de)大路,并為高唐縣經濟(ji)建(jian)設(she)打下(xia)了(le)良好(hao)的(de)基礎。現將本合同(tong)段(duan)的(de)施工狀況總結如(ru)下(xia):
一、工程(cheng)地理位置圖
高(gao)唐(tang)村(cun)村(cun)通大路谷官(guan)屯(tun)段(duan)改建工程L1合同(tong)段(duan)經(jing)起(qi)點路段(duan)變更后(hou),起(qi)點樁(zhuang)號(hao)(hao)為(wei)(wei)K0+0000,位(wei)于高(gao)唐(tang)縣(xian)谷官(guan)屯(tun)村(cun),終點樁(zhuang)號(hao)(hao)為(wei)(wei)K1+500,洼里至(zhi)(zhi)十五里鋪(pu)段(duan)起(qi)點樁(zhuang)號(hao)(hao)為(wei)(wei)K0+0000,位(wei)于高(gao)唐(tang)縣(xian)洼里至(zhi)(zhi)十五里鋪(pu),終點樁(zhuang)號(hao)(hao)為(wei)(wei)K4+400,和(he)諧王至(zhi)(zhi)105國(guo)道(dao)改建工程起(qi)點樁(zhuang)號(hao)(hao)為(wei)(wei)K0+0000,位(wei)于高(gao)唐(tang)縣(xian)和(he)諧王至(zhi)(zhi)105國(guo)道(dao),終點樁(zhuang)號(hao)(hao)為(wei)(wei)K1+700,是途(tu)經(jing)高(gao)唐(tang)縣(xian)城通往各村(cun)的主要通道(dao)。
二、工(gong)程規模、承(cheng)包單位(wei)基本(ben)狀況及完成(cheng)的主要工(gong)作量(liang)
(一)工程概況
高唐村村通大路(lu)谷官屯(tun)(tun)段改(gai)建(jian)工(gong)程(cheng)L1合(he)同(tong)段經起(qi)點路(lu)段變(bian)更(geng)后,起(qi)點樁(zhuang)(zhuang)號(hao)(hao)為(wei)K0+0000,位于高唐縣(xian)谷官屯(tun)(tun)村,終(zhong)點樁(zhuang)(zhuang)號(hao)(hao)為(wei)K1+500,原路(lu)面(mian)翻新(xin),冷(leng)再(zai)生基(ji)層(ceng)(ceng),瀝(li)青混凝(ning)土(tu)面(mian)層(ceng)(ceng);洼里至(zhi)十五里鋪(pu)段起(qi)點樁(zhuang)(zhuang)號(hao)(hao)為(wei)K0+0000,位于高唐縣(xian)洼里至(zhi)十五里鋪(pu),終(zhong)點樁(zhuang)(zhuang)號(hao)(hao)為(wei)K4+400,原路(lu)面(mian)翻新(xin),冷(leng)再(zai)生基(ji)層(ceng)(ceng),瀝(li)青混凝(ning)土(tu)面(mian)層(ceng)(ceng);和(he)諧王至(zhi)105國(guo)道(dao)改(gai)建(jian)工(gong)程(cheng)起(qi)點樁(zhuang)(zhuang)號(hao)(hao)為(wei)K0+0000,位于高唐縣(xian)和(he)諧王至(zhi)105國(guo)道(dao),終(zhong)點樁(zhuang)(zhuang)號(hao)(hao)為(wei)K1+700,原路(lu)面(mian)翻新(xin),冷(leng)再(zai)生基(ji)層(ceng)(ceng),瀝(li)青混凝(ning)土(tu)面(mian)層(ceng)(ceng);全長7.6公(gong)里。本工(gong)程(cheng)原合(he)同(tong)總價為(wei)萬(wan)元(yuan),變(bian)更(geng)后實(shi)際建(jian)安投(tou)資(zi)約(yue)萬(wan)元(yuan)。本工(gong)程(cheng)由(you)高唐縣(xian)交(jiao)通局大路(lu)科設(she)計,高唐縣(xian)天池監理公(gong)司監理。
(二)承包單位狀況
本公司全稱為"莘縣華通道路(lu)工程建筑有(you)限公司,為國(guo)家三級(ji)大路(lu)工程施工企(qi)業,專司大路(lu)、橋梁、市政及土石方(fang)工程的設計與(yu)施工。公司擁有(you)雄厚(hou)的技術力氣、配套先進的筑路(lu)機械(xie)、牢靠的檢測設備、完善的質(zhi)檢體系和科學的管理體制。
13.2025年工程監理竣工工作總結 篇十三
一、工程概況:
本工程(cheng)(cheng)位(wei)于重(zhong)慶xx大竹林組(zu)團0標準分區010-7、010-8和010-9號地(di)塊,為(wei)xx工程(cheng)(cheng),工程(cheng)(cheng)總用(yong)地(di)面(mian)積平方(fang)米,其中包含37#、38#棟高層(ceng)住宅,地(di)下一層(ceng),地(di)上吊七層(ceng);建筑抗震(zhen)設防類(lei)別(bie)為(wei)丙類(lei),場(chang)地(di)類(lei)別(bie)為(wei)二類(lei);建筑結(jie)構形式(shi):剪力墻、框架(jia)核心(xin)筒框架(jia)結(jie)構;建筑使用(yong)年限50年,抗震(zhen)設防烈度6度,建筑耐火等級(ji)(ji)為(wei)一級(ji)(ji),屋面(mian)防水(shui)等級(ji)(ji)一級(ji)(ji),基(ji)礎采(cai)用(yong)獨立(li)基(ji)礎和條形基(ji)礎。
二、施工情況:
加(jia)強施(shi)工(gong)(gong)(gong)(gong)過(guo)程(cheng)控制(zhi),嚴把原材料復試(shi)和半成(cheng)品、成(cheng)品質量關(guan),嚴格控制(zhi)工(gong)(gong)(gong)(gong)序質量,每個(ge)分(fen)部、分(fen)項工(gong)(gong)(gong)(gong)程(cheng)的(de)(de)關(guan)鍵工(gong)(gong)(gong)(gong)序設立質量管理點(dian),要(yao)求(qiu)施(shi)工(gong)(gong)(gong)(gong)單(dan)位進行(xing)自檢(jian)(jian)、互檢(jian)(jian)、交(jiao)接(jie)檢(jian)(jian)制(zhi)度(du)。工(gong)(gong)(gong)(gong)程(cheng)實施(shi)過(guo)程(cheng)中的(de)(de)質量要(yao)求(qiu)進行(xing)控制(zhi),按先交(jiao)底、后(hou)實施(shi)、先樣(yang)板、后(hou)大(da)面的(de)(de)原則(ze),達到合(he)格標準后(hou),才進入下步工(gong)(gong)(gong)(gong)序施(shi)工(gong)(gong)(gong)(gong)。對(dui)重(zhong)慶市(shi)勘測院移交(jiao)的(de)(de)測量控制(zhi)點(dian)進行(xing)了復核(he)(he)及控制(zhi)點(dian)加(jia)密(mi),對(dui)基(ji)礎的(de)(de)基(ji)槽分(fen)別進行(xing)了放樣(yang)及復核(he)(he)測量。認真進行(xing)技術交(jiao)底,重(zhong)要(yao)工(gong)(gong)(gong)(gong)序交(jiao)驗(yan)(yan)、重(zhong)要(yao)部位均經過(guo)參建(jian)各方的(de)(de)檢(jian)(jian)查及重(zhong)慶兩江新區建(jian)設工(gong)(gong)(gong)(gong)程(cheng)質量監督(du)站的(de)(de)監督(du)驗(yan)(yan)收,方可進行(xing)下道(dao)工(gong)(gong)(gong)(gong)序施(shi)工(gong)(gong)(gong)(gong)。
從20xx年(nian)9月開(kai)工(gong)(gong)(gong)以來,施工(gong)(gong)(gong)單位(wei)對基礎工(gong)(gong)(gong)程(cheng)、主體(ti)工(gong)(gong)(gong)程(cheng)、電氣安(an)裝、給排水工(gong)(gong)(gong)程(cheng)、消防工(gong)(gong)(gong)程(cheng)工(gong)(gong)(gong)程(cheng)進行施工(gong)(gong)(gong),過(guo)程(cheng)中分(fen)部分(fen)項(xiang)工(gong)(gong)(gong)程(cheng)的質(zhi)量經(jing)過(guo)檢(jian)查達到(dao)合(he)格(ge)要求后(hou),進行了分(fen)部分(fen)項(xiang)工(gong)(gong)(gong)程(cheng)的驗收,驗收符(fu)合(he)建筑工(gong)(gong)(gong)程(cheng)施工(gong)(gong)(gong)質(zhi)量驗收統一標準,均全部合(he)格(ge)。
三、監理工作情(qing)況:
我監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)部根據項(xiang)目(mu)特點設置(zhi)了(le)(le)(le)合(he)理(li)(li)(li)(li)的(de)項(xiang)目(mu)監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)部,配備(bei)了(le)(le)(le)經驗(yan)豐富的(de)監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)師(shi),嚴(yan)格(ge)按(an)設計圖紙和相關施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)驗(yan)收規范進(jin)(jin)行(xing)(xing)監(jian)(jian)(jian)(jian)理(li)(li)(li)(li),編制(zhi)了(le)(le)(le)本(ben)工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)規劃(hua)、監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)實施(shi)(shi)(shi)(shi)細(xi)則等,用以指導現場監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)工(gong)(gong)(gong)(gong)作。為確保該工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)合(he)同規定的(de)質(zhi)量目(mu)標,我監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)部在主體給排水及(ji)消防安(an)裝整個施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)過程(cheng)(cheng)(cheng)中,按(an)照“監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)規劃(hua)”、“監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)實施(shi)(shi)(shi)(shi)細(xi)則”、強制(zhi)性標準(zhun)和質(zhi)量通病防治等進(jin)(jin)行(xing)(xing)嚴(yan)格(ge)監(jian)(jian)(jian)(jian)理(li)(li)(li)(li),從施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)技(ji)術準(zhun)備(bei)到施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)技(ji)術、管(guan)理(li)(li)(li)(li)活(huo)動運行(xing)(xing)全過程(cheng)(cheng)(cheng),對(dui)(dui)各分項(xiang)工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)質(zhi)量進(jin)(jin)行(xing)(xing)了(le)(le)(le)檢查驗(yan)收。對(dui)(dui)所(suo)有(you)進(jin)(jin)場原材料、成(cheng)品、半成(cheng)品嚴(yan)格(ge)按(an)要(yao)求(qiu)進(jin)(jin)行(xing)(xing)了(le)(le)(le)見(jian)證(zheng)取樣、復試。隨時(shi)對(dui)(dui)影(ying)響工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)質(zhi)量的(de)因素(su)和質(zhi)量偏差進(jin)(jin)行(xing)(xing)了(le)(le)(le)糾(jiu)正,對(dui)(dui)關鍵工(gong)(gong)(gong)(gong)序(xu)、關鍵部位(wei)(wei)和所(suo)有(you)隱蔽(bi)工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)實施(shi)(shi)(shi)(shi)了(le)(le)(le)旁站監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)和隱蔽(bi)檢查驗(yan)收,有(you)效保證(zheng)了(le)(le)(le)工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)。在整個監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)過程(cheng)(cheng)(cheng)中,便于對(dui)(dui)施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)單(dan)位(wei)(wei)的(de)管(guan)理(li)(li)(li)(li),根據施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)單(dan)位(wei)(wei)的(de)組(zu)織機構對(dui)(dui)應(ying)的(de)設置(zhi)了(le)(le)(le)監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)總部和組(zu)團監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)部,以監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)合(he)同、監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)規劃(hua)和監(jian)(jian)(jian)(jian)理(li)(li)(li)(li)細(xi)則條款為依據,對(dui)(dui)工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)進(jin)(jin)行(xing)(xing)認真地監(jian)(jian)(jian)(jian)理(li)(li)(li)(li),要(yao)求(qiu)施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)單(dan)位(wei)(wei)精心施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)(gong)、嚴(yan)格(ge)管(guan)理(li)(li)(li)(li)。
主要從(cong)以下(xia)幾個方面對工程實施監理工作(zuo):
1.認真熟悉(xi)設計(ji)圖紙、規范(fan)和標準,參加施工圖紙會審(shen)和交(jiao)底。
2.認(ren)真審查(cha)施工單位(wei)提交的(de)施工組(zu)織設(she)計和專項施工方(fang)案(an)及(ji)項目部(bu)的(de)管理人員(yuan)、技術(shu)人員(yuan)的(de)資質(zhi)(zhi)(zhi)以及(ji)到(dao)崗(gang)情況(kuang)和特殊工種(zhong)持(chi)證(zheng)上崗(gang)情況(kuang)。對施工單位(wei)的(de)分包單位(wei)資質(zhi)(zhi)(zhi)進行(xing)審查(cha),要(yao)求施工單位(wei)建立健全質(zhi)(zhi)(zhi)保(bao)體(ti)系,并(bing)對其進行(xing)監(jian)督檢查(cha)。
3.把好(hao)原(yuan)材(cai)(cai)料(liao)質(zhi)量關(guan)(guan),原(yuan)材(cai)(cai)優劣直(zhi)接對(dui)工(gong)(gong)程(cheng)質(zhi)量造成(cheng)影響,是確保工(gong)(gong)程(cheng)質(zhi)量的(de)關(guan)(guan)鍵(jian)。工(gong)(gong)程(cheng)所需的(de)原(yuan)材(cai)(cai)料(liao)、半成(cheng)品、構配件(jian)、進場(chang)存放條件(jian)、現場(chang)配制(zhi)等(deng)加強(qiang)控制(zhi),對(dui)進場(chang)材(cai)(cai)料(liao)必(bi)須具有出廠合格(ge)證并現場(chang)見證取樣(yang)復試合格(ge)后用(yong)于本工(gong)(gong)程(cheng)。
4.抓好(hao)(hao)現場(chang)規范,把(ba)好(hao)(hao)工(gong)(gong)(gong)(gong)(gong)序(xu)關(guan)。嚴格(ge)按圖紙設計和(he)規范要求(qiu)驗(yan)收(shou)(shou)每道工(gong)(gong)(gong)(gong)(gong)序(xu)。嚴格(ge)執(zhi)行(xing)隱(yin)(yin)蔽(bi)工(gong)(gong)(gong)(gong)(gong)程(cheng)驗(yan)收(shou)(shou)制度和(he)工(gong)(gong)(gong)(gong)(gong)序(xu)質量驗(yan)收(shou)(shou)制度,監(jian)督施(shi)(shi)工(gong)(gong)(gong)(gong)(gong)單位(wei)的(de)做(zuo)好(hao)(hao)各(ge)工(gong)(gong)(gong)(gong)(gong)種之間的(de)自檢(jian)、互(hu)檢(jian)、交接檢(jian)查(cha),發現問題及(ji)時處理(li)(li)。各(ge)類(lei)隱(yin)(yin)蔽(bi)工(gong)(gong)(gong)(gong)(gong)程(cheng)均(jun)在施(shi)(shi)工(gong)(gong)(gong)(gong)(gong)單位(wei)自檢(jian)合格(ge)的(de)情況下(xia)(xia)進行(xing)驗(yan)收(shou)(shou),符合設計及(ji)施(shi)(shi)工(gong)(gong)(gong)(gong)(gong)規范要求(qiu)后,才允許進入下(xia)(xia)道工(gong)(gong)(gong)(gong)(gong)序(xu)施(shi)(shi)工(gong)(gong)(gong)(gong)(gong)。施(shi)(shi)工(gong)(gong)(gong)(gong)(gong)過(guo)程(cheng)中做(zuo)到(dao)勤(qin)巡(xun)視、多(duo)檢(jian)查(cha)、重(zhong)落實(shi),按照高(gao)質量、嚴要求(qiu)、突出重(zhong)點的(de)原(yuan)則對工(gong)(gong)(gong)(gong)(gong)程(cheng)嚴把(ba)質量關(guan),以旁站、抽測、抽檢(jian)和(he)文字指令的(de)方式進行(xing)監(jian)理(li)(li)工(gong)(gong)(gong)(gong)(gong)作,共發監(jian)理(li)(li)通知28份。落實(shi)工(gong)(gong)(gong)(gong)(gong)序(xu)間交接檢(jian)查(cha)、隱(yin)(yin)蔽(bi)工(gong)(gong)(gong)(gong)(gong)程(cheng)驗(yan)收(shou)(shou)制度,對分項分部工(gong)(gong)(gong)(gong)(gong)程(cheng)的(de)驗(yan)收(shou)(shou)、轉序(xu)和(he)質量評定,嚴格(ge)按照規程(cheng)規范和(he)質量評定標準進行(xing),不合格(ge)者,必須返工(gong)(gong)(gong)(gong)(gong)處理(li)(li)。
5.抓好(hao)現場規范,做(zuo)好(hao)質(zhi)量通病防治。堅持“驗評分離、強(qiang)化(hua)驗收、完善手(shou)段(duan)”的(de)過(guo)程控制的(de)指導(dao)思想。定(ding)期召開監(jian)(jian)理(li)例(li)會制度(du),組織(zhi)了監(jian)(jian)理(li)例(li)會72次,監(jian)(jian)理(li)部定(ding)期組織(zhi)監(jian)(jian)理(li)例(li)會。
6.加強試(shi)(shi)塊、試(shi)(shi)件(jian)(jian)的監督管理,所(suo)有(you)試(shi)(shi)件(jian)(jian)及試(shi)(shi)塊均(jun)進行(xing)現場(chang)見(jian)證取樣,保(bao)證了試(shi)(shi)件(jian)(jian)、試(shi)(shi)塊結(jie)果的真實性。
7.加強旁站和巡(xun)視檢(jian)(jian)查,對砼(tong)澆搗及(ji)關鍵部位進行全過程的旁站監理,對其他工(gong)序加強巡(xun)視檢(jian)(jian)查驗收(shou),進行動態過程控(kong)制,確保工(gong)程質(zhi)量。
8.根據本(ben)工程實際,要求和監督施工單(dan)位嚴格執行(xing)強制性條文的有關(guan)規(gui)定。
9.抓(zhua)好(hao)現場規范,確保安全(quan)施工(gong)文明生產(chan)。我監(jian)理項目(mu)部(bu)始終堅持“安全(quan)第一、預防為(wei)主”的(de)方(fang)針(zhen)。把安全(quan)生產(chan)工(gong)作(zuo)列入監(jian)理部(bu)議事日程,做到常抓(zhua)不懈,保證(zheng)了(le)工(gong)程安全(quan)順(shun)利完工(gong)。
10.加強資料(liao)的(de)收(shou)集與(yu)整(zheng)理工(gong)作,使(shi)資料(liao)跟(gen)上施(shi)工(gong)進度。認為本(ben)單(dan)位工(gong)程施(shi)工(gong)技(ji)術資料(liao)基本(ben)完(wan)整(zheng)、齊全(quan)、真實,工(gong)程實體施(shi)工(gong)質量能滿足安全(quan)和使(shi)用功能的(de)要求(qiu)。
四、監理內業內容:
由監(jian)理(li)(li)人員(yuan)下(xia)達(da)給施(shi)工(gong)(gong)單位的(de)開工(gong)(gong)、停工(gong)(gong)令等(deng)(deng)相關通知(zhi)等(deng)(deng)文(wen)件(jian),都是以書(shu)面(mian)形式由項(xiang)目監(jian)理(li)(li)部(bu)簽(qian)發(fa),真正把(ba)工(gong)(gong)程(cheng)問題落實(shi)到書(shu)面(mian)上,使(shi)得(de)現(xian)場(chang)(chang)監(jian)理(li)(li)人員(yuan)能夠(gou)有(you)理(li)(li)有(you)據地開展監(jian)理(li)(li)和(he)審查工(gong)(gong)作(zuo)。現(xian)場(chang)(chang)的(de)`監(jian)理(li)(li)資(zi)料(liao)(liao)管理(li)(li)過程(cheng)中,根據實(shi)際情(qing)況需(xu)要,監(jian)理(li)(li)公司編制了實(shi)用性(xing)很強(qiang)的(de)監(jian)理(li)(li)資(zi)料(liao)(liao)表(biao)格,如(ru):旁站監(jian)理(li)(li)記錄、工(gong)(gong)程(cheng)試(shi)驗臺帳(zhang)、安全(quan)文(wen)明施(shi)工(gong)(gong)記錄等(deng)(deng)等(deng)(deng),確(que)保現(xian)場(chang)(chang)監(jian)理(li)(li)資(zi)料(liao)(liao)實(shi)現(xian)表(biao)格化,并實(shi)行文(wen)件(jian)隨(sui)時(shi)發(fa)送(song)、隨(sui)時(shi)登記的(de)制度,實(shi)現(xian)場(chang)(chang)所有(you)文(wen)件(jian)都能做到系統管理(li)(li)。項(xiang)目監(jian)理(li)(li)部(bu)進駐(zhu)現(xian)場(chang)(chang)后,便著手進行工(gong)(gong)程(cheng)技術資(zi)料(liao)(liao)微機管理(li)(li),所有(you)的(de)工(gong)(gong)程(cheng)技術資(zi)料(liao)(liao)全(quan)部(bu)及時(shi)輸入(ru)微機,上報的(de)材料(liao)(liao)和(he)文(wen)件(jian)全(quan)部(bu)由微機輸出,使(shi)得(de)資(zi)料(liao)(liao)的(de)管理(li)(li)趨于科學化和(he)規范(fan)化。
1.編(bian)制(zhi)《監理(li)規(gui)劃與細則》。
2.審閱、批復與簽(qian)發開(kai)工(gong)(gong)令:審閱《施工(gong)(gong)合同》和《施工(gong)(gong)組織設(she)計》,并批復《施工(gong)(gong)組織設(she)計》,簽(qian)發開(kai)工(gong)(gong)令。
3.復核與驗算(suan):對施工單(dan)位報送的檢測資(zi)料進行復核與驗算(suan),檢查復核測量(liang)放線資(zi)料。
4.發送通(tong)(tong)知:對施(shi)(shi)工現(xian)場出現(xian)的(de)(de)不符合施(shi)(shi)工合同、設計、施(shi)(shi)工規(gui)范要求(qiu)的(de)(de)行為和要求(qiu)施(shi)(shi)工單位引起注意的(de)(de)事(shi)項填(tian)發監理通(tong)(tong)知,要求(qiu)整改或返工。
5.計量與核(he)(he)(he)算(suan):對已完(wan)工序或分項進行核(he)(he)(he)實現場檢測資料、隱(yin)蔽資料,核(he)(he)(he)算(suan)已完(wan)工序的計量資料。
6.監理(li)內務:填(tian)寫監理(li)報表(biao)、日記,整理(li)監理(li)文件(jian)及資(zi)料,張貼(tie)施工(gong)形象進度等需要(yao)上(shang)墻的(de)資(zi)料。
7.報(bao)送(song)月報(bao)及(ji)發送(song)匯報(bao)資料:按(an)規定(ding)向業主有關部門和單位(wei)發送(song)各(ge)種報(bao)表及(ji)現場協調會匯報(bao)資料。
五、安(an)全、文明(ming)施工情況:
要求(qiu)施工(gong)(gong)(gong)(gong)單(dan)位落(luo)實(shi)施工(gong)(gong)(gong)(gong)責(ze)任(ren)(ren)的(de)同時(shi)落(luo)實(shi)安(an)(an)全(quan)(quan)(quan)責(ze)任(ren)(ren),牢固樹立安(an)(an)全(quan)(quan)(quan)第(di)一的(de)思想,警鐘長鳴。制定了(le)安(an)(an)全(quan)(quan)(quan)管理(li)監理(li)細則,其中明確了(le)各個工(gong)(gong)(gong)(gong)種(zhong)在(zai)施工(gong)(gong)(gong)(gong)工(gong)(gong)(gong)(gong)程中應注意的(de)安(an)(an)全(quan)(quan)(quan)事項(xiang)及重(zhong)大事故應急(ji)救(jiu)援預(yu)案等。要求(qiu)監理(li)工(gong)(gong)(gong)(gong)程師每次檢(jian)查現場(chang)質量、進(jin)度(du)的(de)同時(shi),檢(jian)查現場(chang)安(an)(an)全(quan)(quan)(quan),在(zai)各專業(ye)工(gong)(gong)(gong)(gong)程開(kai)展前,針對專業(ye)施工(gong)(gong)(gong)(gong)特點進(jin)行安(an)(an)全(quan)(quan)(quan)技術交底;定期對各施工(gong)(gong)(gong)(gong)單(dan)位進(jin)行安(an)(an)全(quan)(quan)(quan)教育(yu)(yu),并(bing)要求(qiu)施工(gong)(gong)(gong)(gong)單(dan)位對班組人員進(jin)行崗前安(an)(an)全(quan)(quan)(quan)教育(yu)(yu)和班前安(an)(an)全(quan)(quan)(quan)提示。
14.2025年工程監理竣工工作總結 篇十四
一、工程完(wan)成情況:
xx水(shui)庫(ku)除險(xian)加(jia)固工程經省、市主(zhu)管部(bu)門批準立(li)項,核定(ding)總投(tou)資1006萬元,其(qi)中(zhong):國債資金投(tou)資700萬元,地方配套資金306萬元。該水(shui)庫(ku)除險(xian)加(jia)固建筑的主(zhu)要內容(rong)為(wei):
①、大壩(ba)前壩(ba)坡1563高程以上(shang)改(gai)為漿砌塊石建筑,加固上(shang)游壩(ba)坡建筑,在大壩(ba)左壩(ba)肩心墻與溢洪道右(you)側(ce)墻接(jie)觸面的齒墻后增設一(yi)道砼防滲墻。
②、加(jia)固溢洪道及下游河道治理。
③、更(geng)換(huan)弧形工作門(men)及(ji)平板檢修門(men),更(geng)換(huan)弧門(men)啟(qi)閉機。
④、加固改造上壩及進庫(ku)公路。
⑤、增設(she)大壩(ba)觀測設(she)施與自動化控(kong)制系統。
工(gong)程(cheng)(cheng)于20xx年(nian)5月31日開工(gong)建(jian)設(she)(she),20xx年(nian)6月底全面(mian)竣工(gong),歷(li)時13個月,除(chu)險(xian)加(jia)固(gu)工(gong)程(cheng)(cheng)按照設(she)(she)計(ji)批準的方案已完(wan)成(cheng)(cheng)(cheng)了主要(yao)工(gong)程(cheng)(cheng),即:完(wan)成(cheng)(cheng)(cheng)了大壩(ba)前壩(ba)坡(po)加(jia)固(gu)工(gong)程(cheng)(cheng);溢洪道(dao)加(jia)固(gu)及(ji)下(xia)游河(he)道(dao)治理工(gong)程(cheng)(cheng);完(wan)成(cheng)(cheng)(cheng)上壩(ba)公路(lu)加(jia)固(gu)工(gong)程(cheng)(cheng),包括17公里的公路(lu)護坡(po)及(ji)32公里的瀝青路(lu)面(mian)鋪設(she)(she),以及(ji)公路(lu)橋(qiao)1座,過洪涵洞6座;完(wan)成(cheng)(cheng)(cheng)輸(shu)水(shui)泄洪洞事故(gu)門、工(gong)作門、啟閉設(she)(she)備(bei)制安(an)工(gong)程(cheng)(cheng);完(wan)成(cheng)(cheng)(cheng)大壩(ba)自動化監測(ce)設(she)(she)備(bei)的安(an)裝及(ji)其它(ta)工(gong)程(cheng)(cheng)等,由于受地方配套資金影響大壩(ba)砼(tong)防滲(shen)墻工(gong)程(cheng)(cheng)未(wei)能完(wan)成(cheng)(cheng)(cheng)和壩(ba)體(ti)滲(shen)流(liu)水(shui)位測(ce)量儀(yi)未(wei)安(an)裝,其余主體(ti)工(gong)程(cheng)(cheng)建(jian)筑(zhu)均已按設(she)(she)計(ji)要(yao)求完(wan)成(cheng)(cheng)(cheng)。
該工(gong)(gong)程(cheng)(cheng)共完成(cheng)投資(zi)額(e)萬(wan)(wan)(wan)元(不(bu)包括待驗費20萬(wan)(wan)(wan)元),完成(cheng)主要(yao)工(gong)(gong)程(cheng)(cheng)量為:土石(shi)方開(kai)挖8萬(wan)(wan)(wan)m,土石(shi)方回填x萬(wan)(wan)(wan)m,漿(jiang)砌石(shi)x萬(wan)(wan)(wan)m,砼5萬(wan)(wan)(wan)m,耗用(yong)水泥1782t,鋼(gang)筋(jin)(鋼(gang)材(cai))40t,木(mu)材(cai)11m,瀝青93m,勞(lao)動工(gong)(gong)日5個工(gong)(gong)日。
二、驗收條(tiao)件檢查結(jie)果:
依據(ju)水(shui)(shui)利(li)部的(de)有(you)關(guan)規定,該工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)建(jian)筑按設(she)計要(yao)求已(yi)完(wan)(wan)成(cheng)了(le)主要(yao)工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)施(shi)工(gong)(gong)(gong)(gong)任(ren)務,雖然受(shou)地方配(pei)套資(zi)金影(ying)(ying)響使(shi)個別(bie)尾工(gong)(gong)(gong)(gong)未(wei)能完(wan)(wan)工(gong)(gong)(gong)(gong),但不影(ying)(ying)響工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)正(zheng)常(chang)安全(quan)運(yun)用。工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)建(jian)筑投資(zi)使(shi)用合理,竣(jun)工(gong)(gong)(gong)(gong)決(jue)算已(yi)經完(wan)(wan)成(cheng)并(bing)通過了(le)竣(jun)工(gong)(gong)(gong)(gong)審計。竣(jun)工(gong)(gong)(gong)(gong)資(zi)料(liao)已(yi)準備齊全(quan),工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)施(shi)工(gong)(gong)(gong)(gong)質(zhi)(zhi)量(liang)已(yi)通過了(le)xx市水(shui)(shui)利(li)基本建(jian)設(she)質(zhi)(zhi)監(jian)站的(de)`質(zhi)(zhi)量(liang)檢驗(yan),并(bing)出(chu)具(ju)了(le),工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)質(zhi)(zhi)量(liang)合格。在工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)完(wan)(wan)工(gong)(gong)(gong)(gong)試(shi)運(yun)行(xing)中,工(gong)(gong)(gong)(gong)程(cheng)(cheng)(cheng)能正(zheng)常(chang)運(yun)行(xing),經濟效益(yi)和社會效益(yi)顯著,已(yi)具(ju)備正(zheng)式驗(yan)收條件(jian)。
三、驗收組(zu)織準備情(qing)況:
xx水庫除(chu)險加(jia)固(gu)工(gong)程(cheng)建筑(zhu)項目(mu)法(fa)人已編制(zhi)完成了和(草(cao)稿(gao)),工(gong)程(cheng)建筑(zhu)設(she)計、施工(gong)、監理、運行管理等(deng)單位均已編制(zhi)完成了相應(ying)的(de)“工(gong)作(zuo)(zuo)報告”。依(yi)據的(de)有關規定,項目(mu)法(fa)人提請上級(ji)主管部門成立“竣工(gong)驗(yan)收委員會”,負責xx水庫除(chu)險加(jia)固(gu)工(gong)程(cheng)的(de)竣工(gong)驗(yan)收工(gong)作(zuo)(zuo)。
四、建議驗收時間、地(di)點和參加單位:
根據工(gong)程建筑完(wan)成情況和省(sheng)、市主管(guan)(guan)部門的相關要(yao)求,xx水(shui)庫除險(xian)加固(gu)工(gong)程竣(jun)工(gong)驗(yan)收(shou)(shou)工(gong)作建議擬定于xx年xx月xx日進行(xing),驗(yan)收(shou)(shou)地點在(zai)xx,參加單位(wei)有(you)省(sheng)水(shui)利廳、xx市水(shui)電局、財政局、計劃局、xx河流域水(shui)資源管(guan)(guan)理局及項目法人(ren)、設計、監(jian)理、施工(gong)、質量(liang)監(jian)督、運(yun)行(xing)管(guan)(guan)理等(deng)有(you)關單位(wei)。
綜上所述,xx水(shui)庫除險加固工(gong)程已具備竣工(gong)驗收條件,懇請上級主管部門安(an)排正式(shi)驗收。
15.2025年工程監理竣工工作總結 篇十五
從5月18日至5月31日為期不到半個月的(de)時間里,在(zai)園林局的(de)正確領導和(he)各個施(shi)(shi)工(gong)單(dan)位的(de)大力(li)配(pei)合(he)下(xia),御河西路兩側綠化(hua)帶(dai)施(shi)(shi)工(gong)階段(duan)后期現(xian)場整改工(gong)作已圓滿結束,現(xian)簡(jian)單(dan)總結如下(xia):
一、工程完成情況:
在甲方(fang)代表和設計方(fang)的(de)協同下(xia),全線(xian)工程進展比(bi)較順利,監(jian)理方(fang)對施工過程進行了全過程、全方(fang)位的(de)監(jian)控,現場共計增加栽植苗(miao)木。
二、病(bing)蟲害防治(zhi)情況:
到目前為止,全線對(dui)苗(miao)木病蟲(chong)(chong)害進(jin)行(xing)大力(li)防治(zhi),特別是(shi)對(dui)油松小(xiao)蠹蟲(chong)(chong)的觀察和防治(zhi)。油松小(xiao)蠹蟲(chong)(chong)只在太原開發(fa)標段發(fa)現存有(you)一(yi)株,對(dui)其油松苗(miao)木進(jin)行(xing)了焚燒(shao)處理,并(bing)在全線進(jin)行(xing)了凈(jing)蟲(chong)(chong)劑(ji)藥物噴(pen)施(shi)。近(jin)期發(fa)現山杏、山桃、紅瑞木等部(bu)(bu)分(fen)苗(miao)木有(you)小(xiao)介殼蟲(chong)(chong)、蚜蟲(chong)(chong)、瓢蟲(chong)(chong)等蟲(chong)(chong)害出現,要求各單位不同程度地噴(pen)施(shi)了氧化樂(le)果、除蟲(chong)(chong)凈(jing)、敵敵畏、3911和氯氰菊酯等藥物噴(pen)施(shi),并(bing)對(dui)其樹(shu)干(gan)進(jin)行(xing)了部(bu)(bu)分(fen)涂白(bai),有(you)的標段在苗(miao)木根部(bu)(bu)打了生根劑(ji)。
三、施工過程的監理控制:
始終把質(zhi)量和進度放(fang)在首位(wei),對于施(shi)工(gong)隊進行(xing)(xing)了(le)全(quan)過程的(de)監理(li),特別是有出現(xian)延期跡象的(de)施(shi)工(gong)單(dan)位(wei),采取現(xian)場(chang)口頭指令、現(xian)場(chang)催促、巡(xun)視(shi)查看、發放(fang)整改單(dan)等監理(li)措施(shi),并采用召開現(xian)場(chang)施(shi)工(gong)協(xie)調(diao)會議(yi)和個別施(shi)工(gong)單(dan)位(wei)協(xie)調(diao)會的(de)方式進行(xing)(xing)催促,同時注重安全(quan)文明施(shi)工(gong)。
四、今(jin)后還要加強(qiang)注意的幾點事(shi)宜:
(1)對于近期(qi)新栽的(de)苗(miao)木加大(da)后(hou)期(qi)養護力度:注(zhu)意采(cai)取遮陰(yin)措(cuo)施(shi),特別(bie)是景(jing)天(tian)、衛毛球等苗(miao)木提防日灼。
(2)對于苗木(mu)病蟲害防治,繼(ji)續認真(zhen)觀察并及時防治,建(jian)議各標(biao)段采取聯合防治辦法,并保(bao)持長期性。
(3)注意(yi)藥(yao)物噴施結(jie)束(shu)后,要做有明顯的'提(ti)示標志(zhi)。
(4)對于生長勢弱的苗(miao)木(mu)(mu),加強土(tu)壤的施肥并注意(yi)苗(miao)木(mu)(mu)修(xiu)剪。
(5)對遺漏項(xiang)目要求(qiu)進(jin)行快速增補:現場(chang)還有(you)許(xu)多空缺部分(fen)需要栽植或加密(mi),如井(jing)蓋周(zhou)圍、塌(ta)陷(xian)地(di)段、花灌木澆水時的(de)隔(ge)離土(tu)埂、人為踐踏后(hou)留下的(de)小(xiao)路(lu)、路(lu)燈周(zhou)圍等部分(fen)地(di)段。
(6)及時清(qing)理垃圾雜物,尤其是綠地范(fan)圍(wei)之內(nei)的苗木枯枝枯葉等。
(7)加(jia)強工程(cheng)成品保護,要求各標段成立專門的(de)看護人員。